Define Default Cost Elements
Explanation
This activity is used to relate project cost elements to fields for holding a 
design object's material, work and miscellaneous cost and 
hours. These 
settings are defined on a company template. The project cost elements available in the List 
of Values to be mapped to the Cost Element for Material Cost, Cost Element 
for Work Cost, 
Cost Element for Misc Cost and Cost 
Element for Hours fields are filtered based on the selected company.
Prerequisites
Project cost elements should be defined on the company to be used in the 
mapping. 
System Effects
The fields for holding material, work and miscellaneous cost and hours for a design object will be 
renamed to the description of the project cost elements selected for the  Cost Element 
for Material Cost, Cost Element for Work Cost, 
Cost Element for Misc Cost and Cost 
Element for Hours 
fields.
Window
Default Cost Elements
Related Window Descriptions
Default Cost Elements
Procedure
	- Open the Default Cost Elements 
	window.
- Click New.
- In the Company field, enter the company you are working in or 
	click the List of Values to select a suitable company. A value in 
	this field is required and using % will apply the settings for all 
	registered companies.  
- In the  Cost Element for Material Cost field, enter the project 
	cost element you want to associate with material hours/cost or select one from 
	the List of Values. 
- In the  Cost Element for Work Cost field, enter the project cost 
	element you want to associate with work hours/cost or select one from the List 
	of Values. 
- In the  
Cost Element for Misc Cost field, enter the project cost 
	element you want to associate with miscellaneous hours/cost or select one from 
	the List of Values.
- Similarly in the  Cost 
Element for Hours 
	field, enter the project cost element you want to associate with hours/cost 
	of hours or select one from 
	the List of Values.
- Click Save.