Enter General Server Data
Explanation
Use this activity to specify:
- how many past periods from which to collect historical demand.
- how many future periods for which to create forecasts.
- the default forecast model and its parameters.
- the fields by which you want the parts to be grouped in the Demand Plan
Client.
Prerequisites
N/A
System Effects
There are no system effects until the server is started.
Window
Overview Demand Plan Server
Setup
Demand Plan Server
Setup
Demand Plan Server Setup Wizard
Related Window Descriptions
Overview Demand Plan Server Setup
Demand Plan Server Setup/General
Procedure
- Start the Demand
Plan Server Setup Wizard and go through the steps. Remember that
the wizard only creates one base flow. So if additional flows is wanted then
this have to be done in the
Demand Plan
Server Setup dialog.
- Adding of scheduling information have to be done in
Demand Plan Server Setup/Scheduling dialog.
Or
- To make a new demand plan server, you must open
Overview Demand Plan Server Setup
and press the New button.
- Fill out all mandatory fields.
- Save the setup.
- Open the new Forecast server id in the
Demand Plan
Server Setup dialog and add flows, period versions and scheduling information