Connect Isolation Order to Permit
Explanation
Use this activity to connect existing isolation orders to 
permits. An isolation order can be connected to many permits and a permit can 
have many isolation orders.
In addition, you can create a new isolation order that 
will be automatically connected to the permit. The new isolation order can later 
be prepared in the 
Isolation Order window.
Prerequisites
To connect an existing isolation order:
	- Isolation orders must be defined in 
	
	Isolation Orders.
- The status of the isolation order should be 
	between New and Establishment Completed. Note: If the permit is in the 
	Iso Change state you can only connect isolation orders which are in the 
	Establishment Completed status. 
- The permit should not be approved. Note: If the 
	permit is in the 
	Iso Change state you can only connect isolation orders which are in the 
	Establishment Completed status.
- The maximum number of connections that can exist between 
	a permit type and an isolation type should be defined in 
	Work Order and PM Basic Data/Allowed Connections Permit/Isolation. 
To create and connect a new isolation order
	- The permit should not be approved. Note: If the 
	permit is in the 
	Iso Change state you can only connect isolation orders which are in the 
	Establishment Completed status.
- The maximum number of connections that can exist between 
	a permit type and an isolation type should be defined in 
	Work Order and PM Basic Data/Allowed Connections Permit/Isolation. 
- Isolation types must be defined in 
	Work Order and PM Basic Data.
To create and connect a new isolation order using an isolation 
	- The permit should not be approved. Note: If the 
	permit is in the 
	Iso Change state you can only connect isolation orders which are in the 
	Establishment Completed status. 
- The maximum number of connections that can exist between 
	a permit type and an isolation type should be defined in 
	Work Order and PM Basic Data/Allowed Connections Permit/Isolation. 
- Isolations should be defined and approved in IFS/Equipment.
System Effects
As a result of this activity, isolation orders will be 
created (if applicable) and will be 
connected to the permit. iguana 
Window
Permit
Related Window Descriptions
Permit 
Permit/Isolation Order 
Create Isolation Order 
 
Create Isolation Order from Isolation
Procedure
To connect existing isolation orders
	- Open the 
	Permit window and query for 
	a permit that is not released (F3).
- Click the 
	Isolation Order tab and 
	create a new record (F5). 
- Enter a value in the Isolation Order No. 
	field. Use the List of Values to select a suitable value.
- Save the information (F12).
To create and connect a new isolation order
Alternative 1:
	- Follow step 1 above.
- Right-click on the tab and click Create 
	Isolation Order. The 
	Create Isolation Order 
	dialog box appears.
- Enter a value in the Isolation Type field. 
	Click List to select a suitable value.
- Enter a description for the new isolation order.
- Click OK.
Alternative 2:
	- Follow step 1 above.
- Right-click on the tab and click Create from 
	Isolation Template. The 
	Create Isolation Order from Isolation 
	dialog box appears.
- Enter a value in the Isolation field. Click
	List to select a suitable value.
- Click OK.