Reschedule Work Order Structure

Explanation

This activity is used to reschedule a work order structure by using IFS/Constraint Based Scheduling (IFS/CBS).

Prerequisites

To perform this activity, the work order structure must already be known to the scheduling server. If the work order site is enabled for use with IFS/CBS, this has happened when the work order structure was set to the Prepared status.

System Effects

The work order structure will be rescheduled according to any changed settings on the work order structure, its work orders and/or its operations. For instance, the required start date may have been changed, dependencies between work orders added or removed, or tools added or removed.

As a result of the rescheduling run, the following updates will take place:

Window

Work Order Execution Logic

Related Window Descriptions

Work Order Execution Logic

Procedure

  1. Open the Work Order Execution Logic window and query (F3) for the necessary work order structure.
  2. If there are any changes to be made to the work order structure, like changing dependencies or adding operations, do this first.
  3. Right-click on the header of the window and then click Reschedule Work Order Structure/Project. The Reschedule Work Order Structure/Project dialog box opens.
  4. Select the relevant check boxes:
  1. Click OK. The rescheduling request is now sent to the scheduling server.