The system generates proposed master scheduling receipts as part of the Level 1 process. These receipts exist outside the planning time fence for each part. They are in response to total demand, which is the sum of unconsumed forecasts and actual demand. If demand is inside the planning time fence, the system assigns the proposed receipts to the first workday outside the planning time fence.
The system deletes previous proposed receipts at the beginning of the Level 1 process and regenerates them in response to changes in total demand.
Proposed master scheduling receipts generate demand for capacity, or load, in resource requirements planning (RRP) work centers.