Calculate Lead Time
Explanation
This activity is used to calculate a part's order manufacturing lead time. The
manufacturing lead time is calculated from the default routing and lot size of
the part; it considers the setup, move, operation times, and the efficiency
factor entered for the operation. The system also considers information abut
queue time and shifts, i.e., the number of work hours per day from the work
center where the operation is performed. You specify whether you want to run the
calculation for one part at a time or for all parts in a specific site.
Prerequisites
This activity requires that a part must be defined with a routing.
System Effects
As a result of this activity:
- The system calculates the manufacturing lead time for a part or parts on
a site.
- The system updates these lead time values on the
Inventory
Part/Manufacturing tab in IFS/Inventory.
Window
Lead Time Calculation
Related Window Descriptions
Lead Time
Calculation
Procedure
You can either calculate the lead time directly (Procedure A), or schedule the task as a background job (Procedure B).
A. Calculate the lead time directly:
- Open the Lead Time Calculation dialog
box.
- In the Site field, select the site for which you want to run the
calculation. Use the List of Values to select from available sites.
- If you want to calculate the manufacturing lead time for a specified part,
select the part in the Part No field. Use the List of Values
to select from available parts. If no part is selected, the calculation is
done for all parts in the site.
- In the Update Options list, select the suitable option. Possible
values are Update, Do not update and Update also
expected.
- Click Controls. The Controls for Calculate Manufacturing Lead Time
dialog box opens.
- In the Capacity area, select the required option. The available
options are Average and Demonstrated.
- In the No Routing Option area, select a required option to determine what
can be done if a default routing does not exist for the part. The available options are
Leave Unmodified and Set to Zero.
- In the Leadtime Calculation Basis area, select a required option to
determine the lead time for the part.
- Click OK to close the Controls for Calculate Manufacturing Lead Time dialog box.
- Click OK to close the Lead Time Calculation dialog
box.
B. Calculate the lead time via a scheduled task
-
On the Lead Time Calculation dialog box,
click Schedule. The
Create New Task Schedule
window opens.
-
Set the relevant scheduling parameters and Save. Scheduled tasks can
be seen in Scheduled Database Tasks window.