Calculate Interim Demand Cost

Explanation

Use this activity to calculate the costs for an interim demand.

Prerequisites

If the part is configurable, it must have a configuration attached.

System Effects

Costs will be calculated for the interim demand and can then be compared against a shop order. Costs can be seen in the Costs tab of Interim Order.

Window

Interim Demand Header

Related Window Descriptions

Interim Demand Head
Interim Order/Costs

Procedure

  1. From Interim Demand Header, query on the interim demand whose costs you want to calculate.
  2. Right-click anywhere in the header, then click Calculate Cost.
  3. To store the costs in Inventory Part Configuration when the inventory value is defined as Cost per Configuration,  right-click anywhere in the header. then click Save Standard Cost.
  4. To view the costs, select the Costs tab of Interim Order.