Calculate Interim Demand Cost
Explanation
Use this activity to calculate the costs for an interim demand.
Prerequisites
If the part is configurable, it must have a configuration attached.
System Effects
Costs will be calculated for the interim demand and can then be compared
against a shop order. Costs can be seen in the
Costs tab of
Interim
Order.
Window
Interim Demand Header
Related Window Descriptions
Interim Demand Head
Interim
Order/Costs
Procedure
- From Interim Demand Header, query on the interim demand whose
costs you want to calculate.
- Right-click anywhere in the header, then click Calculate Cost.
- To store the
costs in Inventory Part Configuration when the inventory value is defined as Cost per Configuration,
right-click anywhere in the header. then click Save
Standard Cost.
- To view the costs, select the
Costs
tab of
Interim Order.