Sequence Subtasks within an Instruction

Explanation

This activity is used to perform the definition of a network of subtasks within an instruction. The purpose of this activity is to support the process of sequencing the work for regular maintenance orders with connected tasks (i.e., non-ELS maintenance orders).

Prerequisites

System Effects

Window

Instruction 

Related Window Descriptions

Instruction 
Instruction/Subtasks/Sequencing

Procedure

  1. Open the Instruction window and query (F3) for the necessary instruction (operation).
  2. Click the Subtasks tab and then click the Sequencing sub tab.
  3. Create a new record (F5).
  4. In the Subtask ID field, enter the subtask. Use the List of Values to select a valid value.
  5. In the Preceding Subtask field, enter the predecessor. Use the List of Values to select a valid value.
  6. Save the information (F12).