Schedule Shop Orders/Operations Automatically or Using 
Drag-and-Drop
Explanation
This activity is used to schedule or reschedule shop 
order operations using the Advanced Planning Board (APB), either manually or 
automatically. This can be performed on 
sites which have been set up to use the APB. Scheduling can be carried out either automatically or 
using the drag-and-drop of operations. This activity can be used to move individual 
shop order operations or the entire Dynamic Order Processing (DOP) structures at a 
time.
Prerequisites
	- The shop orders which are to be scheduled must 
	have been loaded to the Advanced Planning Board.
- The shop orders which are to be rescheduled using 
	drag-and-drop must have been scheduled automatically.
- The shop order or structure must have at least one operation in 
	Scheduled or Released state within the APB.
- The operations may not be in Partially Reported or Reported
	state.
System Effects
N/A
Window
Advanced Planning Board
Related Window Descriptions
 Advanced Planning Board
Procedure
Automatic scheduling:
	- In the 
	Activities tab of the Advanced Planning Board, select the shop order for which you want to perform this 
	activity.
- Drag the order into the object table area of the 
	Gantt chart while pressing the Shift key. It will be placed in 
	the object table area with its operations already expanded.
- Select the shop order, right-click and then click
	Scheduling. This will open the Change Schedule window.
- Select the required scheduling options in the 
	Scheduling action(s), Schedule Mode and Resource Assignments
	areas.
- Click OK. The order will be scheduled 
	according to the options selected in step 4. You can see this in the Gantt 
	chart.
Rescheduling operations/DOP structures using 
drag-and-drop:
	- In the 
	Activities tab of the Advanced Planning Board, select the shop order for which you want to perform this 
	activity.
- Drag the order into the object table area of the 
	Gantt chart while pressing the Shift key. It will be placed in 
	the object table area with its operations already expanded.
- Select an operation, right-click and drag it to 
	the left or right and release the mouse button. You can even move the entire shop 
	order, multiple shop orders and DOP structures in this manner as well.