Follow-up Production Schedule
Explanation
This activity is used to review the history logs of actions that have been 
performed for a given production schedule. Material history logs for following 
actions will be registered automatically when one of following material actions 
is performed:
	- 
	Issue material
- 
	Un-issue material
- 
	Receive manufactured product
- 
	Receive by-product
- 
	Un-receive manufactured product
- 
	Un-receive by-product
- 
	Un-receive substitute part
- 
	Scrap product WIP (Work in Progress)
- 
	Un-scrap product WIP
Prerequisites
	- Production Schedule must have been 
	received/scrapped (Report point or Complete) or reversed, to review the 
	relevant material history logs.
System Effects
None
Window
Production Receipt
Production Schedule Material History
Manufacturing Material History
Related Window Descriptions
Production Receipt
Manufacturing Material History
Procedure
Production Schedule Material History:
	- Open  Production Schedule Material History window.
- Query for the required schedule.
- Review the history logs
Manufacturing Material History.
	- Open Manufacturing Material History window.
- Query for the required shop order.
- Review the history logs.