Receipt with Catch Unit Enabled Components 
Explanation
This activity is used to handle receipt with Catch Unit 
(CU) enabled component 
parts in production schedules. A catch unit is enabled to allow a specific
inventory part to manage two parallel units of measure. Information regarding 
both quantities, inventory and catch, are saved on every inventory transaction
record.
Prerequisites
	- A part can be reserved as a catch quantity only if it
is catch unit enabled. 
- If catch unit is enabled for the parent 
part, the quantity reported must have been entered in both the inventory unit of
measure (UoM) and catch UoM.          
	
System Effects
  - The reserved quantities in both the catch UoM and
    inventory 
UoM will be issued during backflush.
- Inventory locations will be updated with 
issued and received quantities.
 
Window
Production 
Receipt 
Production 
Schedule By Line 
Production Schedule By Line Part
Related Window Descriptions
Production 
Receipt 
Production Schedule By Line  
Production 
Schedule By Line Part  
Procedure
From the 
Production Receipt window: 
	- 
	Open the 
	Production Receipt window. 
	
- 
	Populate or query for the appropriate 
	production line and part for which you want to report production. 
- 
	In the Sched Option  list, select
	Scheduled or Unscheduled. 
- 
	In the 
	Structure area, 
	specify either the the structure/routing revision, or the 
	structure/routing alternate. 
- 
	In the  Backflush 
	list, select
	Immediate Backflush or Defer Backflush. 
- 
	Next, enter the quantity to receive in the Quantity 
	Received field. Material can be received into more than one inventory 
	location. If the part is catch unit enabled, enter the catch quantity received in the 
	Catch Quantity 
	Received field. 
- 
	Select the  Edit Components 
	check box and save.
- 
	The 
	Production 
	Receipt Material dialog box will appear. 
- 
	To change the quantity to issue, enter the desired 
	value in Qty to Issue field. 
- 
	
	Save. 
- 
	To reserve the components before backflushing, select 
	the component and then click 
	Assign. The 
	Production 
	Receipt Reservation dialog box appears. 
- 
	In the 
	Production Receipt Reservation 
	dialog box, click Create. The 
	Inventory Part Location
	dialog box appears. 
- 
	In the 
	Inventory Part Location 
	dialog box, select a location and click 
	OK. 
- 
    In the 
	Production Receipt Reservation 
	dialog box, enter a value in the Qty Assigned field. Also enter the catch 
	quantity that you want to reserve in the Catch Qty Assigned field.  
	
- 
    Save and then 
	click OK when the reservations are done. 
	
- 
	When you have finished editing and reserving the components, click 
	 OK to run the backflush.  
 
From the 
Production Schedule By Line window:
	- 
	Open the 
	Production Schedule By Line 
	window. 
- 
	Populate or query for the appropriate 
	production line for which you want to report production. 
- 
	Select the production schedule line for which you
    want to 
	report production. Right-click and then click
	
	Production Receipt.
- 
	The 
	Production Receipt 
	dialog box appears. 
	
- 
	In the 
	Production Receipt 
	dialog box, specify how many parts you want to report and receive into inventory 
	in the Qty Reported field. The scheduled quantity is the default value.
	
- 
	In the  Sched Option list, select 
	 
	Scheduled or Unscheduled. 
- 
	In the 
	Backflush list, select 
	
	Immediate Backflush or 
	Defer Backflush. 
- 
	In the 
	Structure area, specify the structure revision and the structure alternate. If desired, 
	you can specify the routing revision and the routing alternate. 
- 
	In the 
	Location area, select the 
	
	Complete check box to create a complete production receipt. 
	
- 
	In the 
	Location area, click 
    in the 
	Location No field and then click 
	List to choose from different 
	inventory locations. 
- 
	To edit components, click 
	Components. The 
	Production Receipt Material dialog box will appear. 
	
- 
	In the 
	Production Receipt Material 
	dialog box, type a value in the Qty To Issue field. 
- 
	To change the components, click  
	New. In the Part To Issue 
    field, enter or select an available part from the List of Values. Next,
    enter a value in Qty to Issue field. 
- 
	
	Save. 
- 
	To reserve the components before backflushing, select 
	the components and then click 
	Assign. The 
	Production 
	Receipt Reservation dialog box will appear. 
- 
	In the 
	Production Receipt Reservation 
	dialog box, click Create. The 
	Inventory Part Location 
	dialog box will appear. 
- 
	In the 
	Inventory Part Location 
	dialog box, select a location. Click  
	OK. 
- 
    In the 
	Production Receipt Reservation 
	dialog box, enter a value in the Qty Assigned field. Also enter the catch 
	quantity that you want to reserve in the Catch Qty Assigned field.    
- 
    Save and then 
	click OK when the reservations are done. 
- 
	When you have finished editing and reserving the components, click 
	OK  to run the
    backflush.
 
From the 
Production Schedule By Line Part window:
	- 
	Open the Production Schedule by Line Part 
	window. 
- 
	Populate or query for the appropriate part for 
	which you want to report production. 
- 
	Select the production schedule line for which you want
    to report production. Right-click and then click 
	Production Receipt. The 
	Production Receipt dialog box appears. 
	
- 
	In the 
	Production Receipt 
	dialog box, specify how many parts you want to report and receive into inventory 
	in the Qty Reported field. The scheduled quantity is the default value.
	
- 
	In the  Backflush 
	list, select 
	Immediate Backflush or  
	Defer Backflush. 
- 
	In the  
	Structure 
	area, specify the structure revision and the structure alternate. If you
    want, 
	you can specify the routing revision and the routing alternate. 
- 
	Select the Complete check box to create a 
	complete production receipt. 
- 
	In the 
	Location area, click 
    in the 
	Location No field and then click  
	List 
	to choose from different 
	inventory locations. 
- 
	To edit the components, click 
	Components. The 
	Production Receipt Material dialog box appears.
- 
	In the 
	Production Receipt Material 
	dialog box, enter a value in the Qty To Issue field. 
- 
	To change the components, click 
	New. In the Part To Issue 
    field, enter or select 
	an available part from the List of Values. Next,
    enter a value in Qty to Issue field. 
- 
	Save. 
- 
	To reserve the components before backflushing, select 
	the components and then click 
	Assign. The 
	Production 
	Receipt Reservation dialog box will appear.
- 
	In the 
	Production Receipt Reservation 
	dialog box, enter a value in the Qty Assigned field. Also enter the catch 
	quantity that you want to reserve in the Catch Qty Assigned field.    
- 
	Save and then 
	click OK when the reservations are done.
- 
	When you have finished editing and reserving the components, click 
	OK  
	to run the backflush.