Report Point Receipt with Edit Components
Explanation
This activity is used to report production with edit components at a defined report point.
This allows you to edit a copy of the product structure to include component substitutions
or variations. You also can create manual assignments for a given structural component for
specific locations, lot/batches, deviation numbers, etc. These are issued when backflush
occurs. You cannot report more quantities than the reported quantity at a previous report point,
i.e., quantities must be reported through each defined report point. 
Prerequisites
	- This activity requires that a production schedule exists.
- A part must be associated
with a production line.
- A report point must be defined for the production line. 
System Effects
As a result of this activity:
	- The system backflushes the components and operations used
up to a defined report point. 
- The report point balance is updated for the specific report
point.
- If a routing is defined, all operation steps falling between this report point and
the previous one are backflushed at standard cost.
- Operation-linked components used by the
reported operations are backflushed.
- Material not linked to operations is assumed to be
required at the start of the production and is backflushed at the first report point. 
	
- If
inbound locations are defined, they are used by the backflush in its search hierarchy.
- If
an alternate component substitution sequence is defined, it is used by the backflush when
issuing material.
- Inventory transactions are created for the
receipt, as well as all issued components. 
- Operation history transactions are created for
any backflushed machine or labor operations. 
Window
Report
Point Receipt  
Production
Schedule by Line  
Production Schedule
by Line Part
Related Window Descriptions
Report Point Receipt  
Production Schedule by Line  
Production Schedule by Line Part  
Production Receipt  
Production Receipt Material  
Production Receipt Reservation
Procedure
From the 
Report Point Receipt window: 
  - Open the 
	Report Point Receipt window.
- In the 
	Production Line list, select the production line and part for which to report production.
- In the Structure 
	area, specify the structure revision and structure 
	alternate. If desired, you can specify the routing revision and the routing 
	alternate.
- In the  Backflush list, 
	select 
	 Immediate Backflush or 
	Defer Backflush.
- In the Qty Reported field, type the quantity to report at the 
	specific report point. You cannot report more quantities than are reported 
	at a previous report point.
- Select the Edit Components check box.
- Save. The 
	Production Receipt
    Material dialog box will appear.
- In the 
	Production Receipt Material dialog box, type a value in the
    Qty To Issue field. 
- To change components, click 
	New. The cursor appears in the 
	Part To Issue field. Click  
	List 
	to select from available parts. Next, type a value in the Qty
    to Issue field.
- Save.
- To reserve the components before backflushing, select the components, then click 
	Assign.
    The 
	Production Receipt Reservation dialog box will appear.
- In the 
	Production Receipt Reservation dialog box, click 
	Create.
    The 
	Inventory Part Location dialog box will appear.
- In the 
	Inventory Part Location dialog box, selection a location.
    Click OK.
- In the 
	Production Receipt Reservation dialog box, type a value in
    the Qty Assigned field. Save.
- When you are finished editing and reserving components, click  
	OK to run
    the backflush.
From the 
Production Schedule by Line window: 
  - Open the 
	Production Schedule by Line 
	window. 
- In the  
	Production Line 
	list, select the production line for which to report
    production.
- Select the production schedule line for which to report production.
	Right-click and then
    click Production Receipt. The 
	Production Receipt 
	dialog box will
    appear.
- In the 
	Production Receipt dialog box, specify how many parts you
    want to report and receive into inventory in the Qty Reported field. The scheduled
    quantity is the default value.
- In the Backflush list, select 
	Immediate Backflush or 
	Defer
    Backflush.
- In the Structure 
  area, specify the structure revision
    and structure alternate. If desired, you can specify the routing revision and the routing
    alternate.
- In the Location area, select the 
	Report Point check box to create
    a report point receipt.
- In the Location area, specify the report point in the 
	Report Point field. Click
  List to select from available report points.
- To edit components, click 
	Components. The 
	Production Receipt
    Material dialog box will appear.
- In the 
	Production Receipt Material dialog box, type a value in the
    Qty To Issue field.
- To change components, click 
	New. The cursor appears in the 
	Part To Issue field. Click  
	List 
	to select from available parts. Next, type a value in Qty to
    Issue field.
- Save.
- To reserve the components before backflushing, select the components, then click 
	Assign.
    The 
	Production Receipt Reservation dialog box will appears.
- In the 
	Production Receipt Reservation dialog box, click 
	Create.
    The 
	Inventory Part Location dialog box will appear.
- In the 
	Inventory Part Location dialog box, select a location.
    Click OK.
- In the 
	Production Receipt Reservation dialog box, type a value in
    the Qty Assigned field. Save.
- When you are finished editing and reserving components, click  
	OK to run
    the backflush.
From the 
Production Schedule by Line Part window: 
  - Open the 
	Production Schedule by Line Part 
	window. 
- In the Part No list, select the part for which to report production.
- Select the production schedule line for which to report production. 
  Right-click and then click Production Receipt. The 
	Production Receipt 
	dialog box will
    appear.
- In the 
	Production Receipt dialog box, specify how many parts you
    want to report and receive into inventory in the Qty Reported field. The scheduled
    quantity is the default value.
- In the  Backflush list, select 
	 Immediate Backflush or 
	Defer
    Backflush.
- In the Structure 
  area, specify the structure revision
    and structure alternate. If desired, you can specify the routing revision and the routing
    alternate.
- In the  
	Location area, select the 
	 
	Report Point check box to create
    a report point receipt.
- In the  
	Location area, specify the report point in the 
	Report Point field.
    Click List to select from available report points.
- To edit components, click 
	Components. The 
	Production Receipt
    Material dialog box will appear.
- In the 
	Production Receipt Material dialog box, type a value in the
    Qty To Issue field.
- To change components, click 
	New. The cursor appears in the 
	Part To Issue
    column. Click List to select from available parts. Next, type a value in 
	Qty to
    Issue field.
- Save.
- To reserve the components before backflushing, select the components, then click
	 Assign.
    The 
	Production Receipt Reservation dialog box will appear.
- In the 
	Production Receipt Reservation dialog box, type a value in
    the Qty Assigned field. Save, then click 
	OK when the reservations
    are finished.
- When you are finished with editing and reserving components, click  
	  
	OK to
    run the backflush.