Shop Order Load per Department
Explanation
Use this activity to study the workload of a particular department during a specified
interval of time. You can study the workload per day or per week. The graph at the bottom
of the Load per Department window shows either the specified
resource's available capacity or its theoretical capacity. Every load that goes over the capacity line
is overload.
Prerequisites
This activity requires that a defined department be associated
with a work center used in a shop order.
System Effects
As a result of this activity, the system shows a graphical representation of the load
per department.
Window
Load per Department
Related Window Descriptions
Load per Department
Procedure
- Select the department you want to study in the
Department No list. The
current workload within the given time interval appears on the graph.
- If you want to study a workload for another time interval, type the dates in the
From Date and To Date fields.
- To update the graph, reselect the department in the
Department No list.
- If you want to study the workload per week instead of per day, select the
Weekly
check box.
- Select a value in the Show Capacity as list to indicate how
capacity should be calculated for the graph.