Unscheduled Receipt
 
Explanation
 
This activity is used to report production that was performed but not scheduled.
Note: Labor and operation setup time for each receipt is calculated as;
 
[(setup time/standard lot size)*receipt quantity]
If standard lot size is not defined, then the total setup time will be reported for every receipt.
 
Prerequisites
 
This activity requires that a part be associated with a production line. 
 
System Effects
 
As a result of this activity, the system backflushes the components and operations used
in the manufacturing process. When making an unscheduled receipt, the system does not
automatically update the production schedule. If inbound locations are defined, they are
used by the backflush in its search hierarchy. If outbound locations are defined, they are
used as default receiving location for production on the production line. If an alternate
component substitution sequence is defined, it is used by the backflush when issuing
material. Inventory transactions are created for the receipt and all
issued components. Operation history transactions are created for any backflushed machine
or labor operations. Quantities of the backflushed
parts, received and 
issued in catch unit, will be saved on the record if it is 
entered.  
 
Window
 
Production
Receipt 
Production
Schedule by Line 
Production Schedule
by Line Part
 
Related Window Descriptions
 
Production Receipt
Production Schedule by Line
Production Schedule by Line Part
 
Procedure
 
From the  
 
Production Receipt 
 
window: 
 
  - Open the Production Receipt window. 
- In the Production Line list, select the production line and part for which
    to report production.
- To make an unscheduled receipt, select  Unscheduled 
	in the  Sched Option
    list. 
- In the Structure 
	area, specify the structure revision and
    structure alternate. If desired, also specify the routing revision and the routing
    alternate.
- In the  Backflush list, specify whether the backflush process should be run
    immediately or deferred.
- Select an inventory location for the part, then enter the quantity to receive into this
    inventory location in the Quantity Received field. You can receive into more than one
    inventory location. If the part is catch unit enabled, 
	the catch quantity should also be entered.
 
- To change inventory locations, click 
	New. Click in the Location No
	field, then
    click 
	 List to choose from available locations. In the 
	Quantity Received field, enter the quantity of parts to receive. 
- Save.
From the  
 
Production Schedule by Line 
window: 
 
  - Open the Production Schedule by Line window. 
- In the Production Line list, select the production line for which to report
    production.
- Select the production schedule line for which to report production. 
	Right-click and then click Production Receipt. The Production Receipt 
	dialog box will appear.
- In the Production Receipt dialog box, specify how many parts to
    report and receive into inventory in the Qty Reported field. The scheduled quantity is the
    default value. If the part is catch unit enabled, the 
	catch quantity should also be entered.
    
- To make an unscheduled receipt, select 
	Unscheduled in the 
	Sched Option
    list. If no scheduled quantities exist for the part, select  
	Unscheduled to
    create the receipt.
- In the Backflush list, specify whether the backflush process should be run
    immediately or deferred.
- In the Structure 
	area, specify the structure revision and
    structure alternate. If desired, also specify the routing revision and the routing
    alternate.
- In the   Location 
	area, select the 
	Complete check box to
    create a complete production receipt.
- In the  
	 Location area, specify the inventory location in which the parts
    are to be received in the Location No field. Use  
	List to select from different
    inventory locations.
- Click OK.
From the Production Schedule by Line Part 
window: 
 
  - Open the Production Schedule by Line Part window. 
- Select the part for which you want to report production in the 
	Part No list.
- Select the production schedule line for which to report production. 
	Right-click and then click Production Receipt. The Production Receipt 
	dialog box will appear.
- In the Production Receipt dialog box, specify how many parts to
    report and receive into inventory in the Qty Reported field. The scheduled quantity is the
    default value. If the part is catch unit enabled, the 
	catch quantity should also be entered. 
    
- To make an unscheduled receipt, select 
	Unscheduled in the 
	Sched Option
    list. If no scheduled quantities exist for the part, select 
	Unscheduled to
    create the receipt.
- In the Backflush list, specify whether the backflush process should be run
    immediately or be deferred.
- In the Structure 
	area, specify the structure revision and
    structure alternate. If desired, also specify the routing revision and the routing
    alternate.
- In the   Location 
	area, select the 
	Complete check box to create a
    complete production receipt.
- In the  
	 Location area, specify the inventory location in which the parts
    are to be received in the Location No field. Use 
	List to select from different
    inventory locations.
- Click OK.