Connect Level 0 Part to MS Set
Explanation
Use this activity to connect a master schedule level 0 part to a master scheduling
set and to enter data for cost and on-hand quantity information for all Level 0
part families. Master Schedule Set 1 is used for the actual master schedule;
others can be used for various forecasts and scenarios. The List of Values for
master schedule sets shows only those master schedule sets for which forecasts
have been entered for the site, and part numbers entered by the user.
Prerequisites
This activity has the following prerequisites:
- The master scheduling level 0 part has been registered
- The master schedule set has been defined.
System Effects
As a result of this activity, a master schedule level 0 part is connected to a selected
master schedule set.
Window
MS Basic Data
Related Window Descriptions
MS Basic Data/Family Set
Data
Procedure
- Open the MS Basic Data window.
- Populate to view the existing data.
- Select New.
- In the Site column, specify the site for which you want to connect the part. Use
the List
of Values to select from available sites.
- In the Part No column, specify the part family you want to connect to a master schedule set.
Use the List of Values to select from available part families. The part
description will automatically fill in.
- In the Master Schedule Set column, specify which master schedule set you want to
connect the selected part. Use the List of Values to select from available sets.
- Save the changes.