Disaggregate Family Plan
Explanation
Use this activity to disaggregate a family production plan to item production plans.
The family production plans will be exploded through the planning bill percentages.
Prerequisites
This activity requires that a production plan for the family level must exist.
System Effects
As a result of this activity, the disaggregation places the item production quantity in
the option forecast at the item level.
Window
Disaggregate
Level 0
to Level 1
Related Window Descriptions
Disaggregate Level 0 to
Level 1
Procedure
You can execute disaggregate family plan either directly (Procedure A) or
schedule the disaggregation by using New
Database Task Schedule. (Procedure B).
Procedure A
- Select the site for which the family plans should be disaggregated. Use the List button
to select from available sites. If you leave this field blank, all sites will be
disaggregated.
- In the Part No field, specify for which part the disaggregation should take place. Use
the List button to select from available parts. It this field is left blank, all
parts will be disaggregated.
- In the MS Set field, select the master schedule set for which the family plan should be
disaggregated. Use the List button to select from available sets.
- In the MS Set field, select the master schedule set you want to receive the
disaggregated family plan. Use the List button to select from available sets.
- In the Run Date field, specify the date when you want to perform the disaggregation.
- Click OK.
Procedure B
Click Schedule and set the parameters in the New Database Task
Schedule to schedule the
disaggregate item production planning. A schedule task will be created once the
setup is completed.