Disaggregate Family Plan

Explanation

Use this activity to disaggregate a family production plan to item production plans. The family production plans will be exploded through the planning bill percentages.

Prerequisites

This activity requires that a production plan for the family level must exist.

System Effects

As a result of this activity, the disaggregation places the item production quantity in the option forecast at the item level.

Window

Disaggregate Level 0 to Level 1

Related Window Descriptions

Disaggregate Level 0 to Level 1

Procedure

You can execute disaggregate family plan either directly (Procedure A) or schedule the disaggregation by using New Database Task Schedule. (Procedure B).

Procedure A

  1. Select the site for which the family plans should be disaggregated. Use the List button to select from available sites. If you leave this field blank, all sites will be disaggregated.
  2. In the Part No field, specify for which part the disaggregation should take place. Use the List button to select from available parts. It this field is left blank, all parts will be disaggregated.
  3. In the MS Set field, select the master schedule set for which the family plan should be disaggregated. Use the List button to select from available sets.
  4. In the MS Set field, select the master schedule set you want to receive the disaggregated family plan. Use the List button to select from available sets.
  5. In the Run Date field, specify the date when you want to perform the disaggregation.
  6. Click OK.

Procedure B

Click Schedule and set the parameters in the New Database Task Schedule to schedule the disaggregate item production planning. A schedule task will be created once the setup is completed.