Evaluate Master Scheduling Level 0 Results

Explanation

This activity is used to evaluate the result of the master scheduling level 0 calculation which is performed when you Aggregate Item Plans.

Prerequisites

This activity requires that the Aggregate Item Plans must have been performed.

System Effects

There are no system effects as a result of performing this activity.

Window

MS Level 0 Part

Related Window Descriptions

MS Level 0 Part
MS Level 0 Part/Register Forecast

Procedure

  1. Open the MS Level 0 Part window.
  2. Populate or query for the required part from the Part No field.
  3. Click the Register Forecast tab and study the result of the master scheduling level 0 calculation.