Perform Project Master Schedule Calculation
Explanation
This activity is used to perform project master scheduling (project
MS) for either a single part, or for all the parts belonging to a
specific site and project planned netting group (PNG). This process uses information from
the forecasted demand that you have entered and the actual backlog of orders. It
calculates forecasted demand and actual orders, traces orders, and provides
action messages. When initiating a project MS process for
a site or PNG you may set it up so that project material requirements planning (PMRP)
and material requirements planning (MRP) are run immediately after project MS.
Prerequisites
This activity requires that:
- A project MS part needs to be
defined.
- Forecasted demands need to be registered.
System Effects
As a result of this activity:
- If you perform project MS for a site or PNG, one or more
background jobs will be executed to perform project MS and, optionally, PMRP
and/or MRP.
- The project MS process generates proposals as required.
Shop order requisitions and purchase requisitions may also be created for
fixed proposals, if you have indicated that requisitions need to be created.
During the process, existing proposals and requisitions in Planned
state for the part are removed and new ones will be created if necessary.
These proposals are created for the forecast activities.
- Material transfer requisitions may also be created to transfer material
between activities.
- Action messages may be displayed in the
Project MS Part/Action Messages tab.
- The gross demand per activity is made available
and this forms the basis for the MRP calculation.
- The projected quantity of the part on-hand is
analyzed and displayed in the Projected Balance field in the
Project MS Part/Register Forecast tab. The
physical quantity on-hand is also updated. This value is used to calculate
the development of quantity on-hand and the quantity available to promise.
Window
Project MS Part
Calculate Project MS
Related Window Descriptions
Project
MS Part
Calculate Project MS
Procedure
To perform project MS for a single part:
- Open the Project MS Part window and query for the desired
project MS part.
- Right-click anywhere in the header and then click
Run Project MS. The Calculate Project Master Scheduling for a
Single Part dialog box appears.
- Change the value in the Run Date field if
necessary and then click OK.
To perform project MS for a site or PNG:
- Open the Calculate Project MS dialog box.
- In the Site field, enter the short code of
the site for which you want to perform project MS, or select it from the List of
Values. If you enter % here project MS will consider all your sites during the
calculation.
- In the PNG field, enter the ID of the
desired PNG. If you enter % here project MS will consider all the PNGs that exist
in the selected site(s).
- In the Run Date field, enter the date when
you want to perform the calculation.
- Select the Stop Project MS on Error check box if
you want the project MS process to stop when errors are encountered.
- Select the Start PMRP once Project MS is
completed check box if you want PMRP to be performed after project MS.
- Select the Start MRP once Project MS is
completed check box if you want MRP to be performed after project MS.
- Click OK.