Update Level One Parts
Explanation
This activity is used to update the roll flag, the time fence and the family
type of the level one parts, that belong to the planning structure of the level
0 part.
Prerequisites
- The level 0 part should be defined in the
MS Level 0
Part window and the
MS Level
1 Part
window or
the respective level 1 parts are already
created using the
Disaggregate Level
0 to Level 1 window.
System Effects
As a result of this activity, the roll flag, time fence and the family type
will be updated from level 0 to level 1.
Window
MS Level
0 Part
Related Window Descriptions
Master Scheduling Level 0 Part
Procedure
- Open the
MS Level
0 Part window and query
for the required part.
- Change the required data.
- Right-click and then click Update Level 1 Parts.
- The required changes you made in this window, will be updated in the
MS Level
1 Part window.