Manage Action Verification
Explanation
This activity is used to verify the corrective and preventive action. This means that a third party has confirmed that the corrective and preventive action is completed, and that the corrective and preventive action result is satisfying.
Prerequisites
A corrective and preventive action in the Completed status should exist.
System Effects
As a result of this activity, the status of the corrective and preventive action changes to
Verified.
Window
Corrective and Preventive Action
Corrective and Preventive Actions
Related Window Descriptions
Corrective and Preventive Action
Corrective and Preventive Actions
Procedure
- In the
Verification Notes field under the Verification Details area
in the Corrective and Preventive Action window,
enter an appropriate note. Entering a value in this field is mandatory.
- In the Responsible ID field under the Effectiveness Details area,
enter the ID of the effectivness evaluation responsible person. Entering a
value in this field is mandatory.
- In the Target Date field under the Effectiveness Details area, enter a
target effectivness evaluation date. Entering a value in this field is optional.
- Click Save.
- Right-click and then click Verify. The status of the corrective and preventive action record changes to
Verified. The system generates a time stamp for the verification date as well as for the person who made the system state change.