Use this activity to create a new preventive maintenance action revision (PMA revision) from an existing revision.
A PMA revision that is in use (i.e., a revision where work orders have been generated) can only be updated with restriction. Major changes such as entering new jobs, changing maintenance organization, etc, cannot be performed. When major changes are required, a new PMA revision has to be created.
New revisions can be created from PMA revisions in Active and Obsolete statuses if there is no PMA revision currently in the Preliminary status.
A PMA revision in Active or Obsolete status should exist in the system and a PMA revision in Preliminary status should not exist.
As a result of this activity, a new PMA revision is created. The revision will have the Preliminary status.
Separate PM Action
Route PM Action
Separate PM Action
Route PM Action
Create New Revision for PM