Enter Inventory Or Non Inventory Part

Explanation

Use this activity to plan material lines that is required for a PM action. You can adjust the expected material requirement during planning. You are allowed to enter inventory parts as well as purchase parts.

Prerequisites

System Effects

As a result of this activity, a material line will be connected to the PM action.

Window

Separate PM Action
Route PM Action

Related Window Descriptions

Separate PM Action 
Separate PM Action/Materials
Route PM Action 
Route PM Action/Materials

Procedure

  1. Open one of the PM action windows (Separate PM Action or Route PM Action).
  2. Click the Materials tab and create a new record.
  3. Enter an appropriate part in the Part No field. Use one of the following methods: 
  1. Enter the condition code if applicable. Use the List of Values to select a suitable value.
  2. Enter the quantity required in the Planned Quantity field.
  3. Enter a value in the Job ID field if you want to organize the material lines according to jobs. Use the List of Values to select a suitable value.
  4. Enter the sales part site and the sales part number if you want to invoice the price of the material to a customer (only applicable to IFS/Service Management).
  5. Save the information (F12).