Follow Up PMRP Action Messages

Explanation

This activity is used to follow up the project material requirements planning (PMRP) action messages, which are produced after PMRP is run. This activity will open appropriate windows for you to take action as suggested by PMRP.

The Follow Up option will not be available for the following messages:

Prerequisites

PMRP must have been run. 
 

System Effects

N/A

Window

 PMRP Action Proposals

Related Window Descriptions

PMRP Action Proposals

Procedure

  1. Open the PMRP Action Proposals  window, and populate it.
  2. Select a record.
  3. Right-click and then click Follow Up.

    For the messages mentioned below, the Follow Up option will be available.
  1. If the part Type is Manufactured, and the Supply Type is Requisition then the follow up menu should bring the Shop Order Requisitions window. Only the shop order requisitions with ProposalCreated status will be populated.
  2. If the part Type is Purchased, and the Supply Type is Requisition then the follow up menu should bring the Purchase Requisition Lineswindow. Only the purchase requisition lines with Planned status will be populated
  1. If the PMRP source is Purchase Order, then the Follow Up option should open the Purchase Order window with the appropriate order number displayed.
  2. If the PMRP source is Shop Order, then the Shop Order window will be opened with the appropriate order number displayed.
  3. If the PMRP source is Request Quote, then the Purchase Requisition window will be opened with the appropriate requisition number displayed. 
     

For the messages listed below, the Follow Up option will open the Inventory Part window with the appropriate values populated for the related Site and Part No fields.