Perform Capacity Requirements Planning
Explanation
Use this function to start calculating the expected future workload of machines and
production groups. You can perform CRP for one site at a time or for all sites to which
you have access.
Prerequisites
- The manufacturing plan from MRP or PMRP must already be complete.
- You must have entered the
work centers you want to work with, specified the unit of measure in which their capacity
is measured, and specified their actual capacity.
- You must have specified if operation
scheduling is done with or without parallel operations.
- You must make sure the shop
calendar is up to date. CRP makes sure that the workload is planned for only those days
included in the shop calendar. Only workdays should exist in the shop calendar, so
weekends and holidays are not counted in CRP.
System Effects
The result from CRP is presented as the total workload per day and work center.
Window
Perform CRP
Related Window Descriptions
Perform CRP
Procedure
You can execute CRP either by direct execution (Procedure A) or by scheduling
the task to execute as a background job (Procedure B).
Procedure A:
- Enter the site for which you want to run CRP in the Site field. Use the
List of Values
for accessible sites. If you leave the field blank, CRP is run for all sites to which you
have access.
- If you want to stop the CRP process when an error occurs, you can select
the Stop CRP On Error check box.
- Click OK.
Procedure B:
Click Schedule to open the
New Database Task Schedule window. Set the scheduling parameters as
desired and save. Scheduled tasks can be seen in Scheduled Database Tasks
window