Enter Part Line, Requisition

Explanation

A purchase requisition is comprised of a requisition header and one or more requisition lines. Once the header has the Planned status, you can create purchase requisition lines.

Requisitions for purchase parts, including external maintenance and repair services, are entered on the Part Requisition Lines tab. Requisitions for parts without part numbers, i.e., no-number parts, are entered on the No Part Requisition Lines tab.

Note that express purchase requisitions, i.e., purchase requisitions with the order code 5 (Express) are not addressed in this activity description.

When you enter a purchase requisition for a new supplier without a supplier record, it is possible to perform a quick registration of the new supplier using an existing supplier as a template. When you do so, supplier information that is not company-specific is automatically copied from the template supplier to the new supplier, while additional information is entered in the Quick Supplier Registration dialog box.

If you want to view a purchase price comparison, you can do so as soon as the part number is entered. Select the line, right-click and then click Price Comparison. In the dialog box that opens, enter the purchase quantity that you want to use for the price comparison.

If the purchase part has condition codes enabled, the default condition code will be used unless another code is specified. If the requisition line is converted to a purchase order, the specified condition code will be used by default on the purchase order line.

If alternate parts are defined for the purchase part, you can view them by selecting the line, right-clicking and then clicking Alternate Purchase Part Base Data. Any specified alternate parts on the site will then be displayed.

When the quantity/date on the Purchase Requisition window has been changed, you can replicate this change to a DOP order. When you update the Quantity/Wanted Receipt Date field on the purchase order line, the Replicate Changes dialog box will be opened.
Note: The Send Change Request check box will have no effect. Even if it is selected, will not apply to DOP.

If you select Yes, Revised Qty Due/Revised Due Date on the connected DOP order, the pegged quantity will be updated. However if the connected DOP order has other supply orders, an error message will appear and no replication will be done. An alarm entry will also be created.
If you select No in the Replicate Changes dialog box, a replication will not be done and an alarm entry will be created to reflect the date mismatch.
One of the following options can be used to handle the alarm entry:

If the over delivery tolerance has not been entered on the Purchase Part window, the tolerance percentage will be taken from the relevant purchase group of the purchase requisition line and transferred to the purchase order line. In an instance where the over delivery tolerance is specified for both the purchase part and the purchase group connected to it, the value defined for the purchase part is considered.

Prerequisites

For external repair orders, several other prerequisites apply:

System Effects

  1. The supplier split data is retrieved for the particular part, site, and period. The desired receipt date should be between the phase-in and the phase-out date.
  2. The system loops through each supplier. The supplier with the highest percentage is processed first by the system.
  3. The split quantity is calculated as follows: Split Qty = Std Multiple Qty * Round (Requisition Qty * Split Percentage/Std Multiple Qty).
  4. A new purchase requisition line is created for each supplier in the supplier split basic data.

The Supplier Split check box is selected on all the requisition lines, and the requested quantity and the split percentage are displayed on each line. The last supplier might not have an even multiple of the standard order quantity. In this case, a message will appear when the requisition line is saved. Note that all the calculations are performed in the inventory unit of measure. After the order quantity is calculated, it is converted to the purchase unit of measure for each supplier.

Window

Purchase Requisition

Related Window Descriptions

Purchase Requisition
Purchase Requisition/Part Requisition Lines

Quick Supplier Registration

Create Supplier for Purchase Part?

Additional Cost Details

Procedure

To enter a purchase requisition line for a previously entered supplier (or when the supplier is not known):

  1. Open the Purchase Requisition window and query for the applicable requisition number.
  2. Click the Part Requisition Lines tab and create a new record.
  3. In the Part No field, enter the part number or select it from the List of Values. If the part you want to enter belongs to an assortment, you can also look up its number by selecting the line, right-clicking and then clicking Parts by Assortment and Site Cluster.
  4. If you want to specify a condition code, select from the available values by using the List of Values in the Condition Code field.
  5. In the Quantity field, indicate the number of parts to be ordered.
  6. In the Wanted Receipt Date field, indicate the date on which the parts are needed.
  7. In the Supplier field, the supplier that is defined as the primary supplier of this part is automatically indicated. You can change the supplier by using the List of Values if several suppliers are defined for the part. If there are suppliers connected to the part but none of them is set as primary, you can select one from the List of Values. You can also leave the Supplier field blank if you do not know which supplier is to be used.
    If no supplier is connected to the part, a message is displayed. It is not necessary to indicate a supplier if the requisition will be converted to a request for quotation.
  8. Save when completed.

To enter a purchase requisition line for a new supplier without a supplier record, using a supplier template:

  1. Open the Purchase Requisition window and query for the applicable requisition number.
  2. Click the Part Requisition Lines tab and create a new record.
  3. In the Part No field, enter the part number or select it from the List of Values. If the part you want to enter belongs to an assortment, you can also look up its number by selecting the line, right-clicking and then clicking Parts by Assortment and Site Cluster.
  4. In the Quantity field, indicate the number of parts to be ordered.
  5. In the Wanted Receipt Date field, indicate the date on which the parts are needed.
  6. Right-click, and then click Quick Supplier Registration. The Quick Supplier Registration dialog box opens.
  7. In the Template Supplier field, enter the ID of the supplier that you want to use as a template. You can either enter the ID manually or click List to choose the ID from a List of Values.
  8. In the New Supplier field, enter the ID for the new supplier.
  9. Enter the name of the new supplier in the New Supplier Name field.
  10. In the Association field, you can enter the association number of the new supplier.
  11. In the Supplier Address fields, enter the complete address for the new supplier.
  12. Click OK to exit the Quick Supplier Registration dialog box.
  13. Save the purchase requisition line when completed. The Create Supplier for Purchase Part? dialog box opens.
  14. In the U/M field, enter the unit of measure that will be used when administering purchase orders for the part from the new supplier. This will serve as both the unit in which the part is purchased, as well as the unit in which the supplier is paid. You can enter the unit of measure manually or by clicking List to choose the ID from a List of Values.
  15. In the Price field, enter the new supplier's price per unit for the part.
  16. Click OK to exit the Create Supplier for Purchase Part? dialog box.

To enter a purchase requisition line when multiple suppliers are defined for the purchase part:

  1. Open the Purchase Requisition window and query for the applicable requisition number.
  2. Click the Part Requisition Lines tab and create a new record.
  3. In the Part No field, enter the part number or select it from the List of Values. If the part you want to enter belongs to an assortment, you can also look up its number by selecting the line, right-clicking and then clicking Parts by Assortment and Site Cluster.
  4. In the Supplier field, the supplier that is defined as the primary supplier of this part is automatically indicated.
  5. In the Quantity field, indicate the number of parts to be ordered.
  6. In the Wanted Receipt Date field, indicate the date on which the parts are needed.
  7. Save when completed. A message appears inquiring whether you want to split the requested quantity. Click Yes and a requisition line will be created for each supplier.

To enter a purchase requisition line for external repair orders:

  1. Open the Purchase Requisition window and query for the applicable requisition number.
  2. Click the Part Requisition Lines tab and create a new record.
  3. In the Part No field, enter the part number or select it from the List of Values. If the part you want to enter belongs to an assortment, you can also look up its number by selecting the line, right-clicking and then clicking Parts by Assortment and Site Cluster.
  4. In the External Service Type field, enter the applicable service type or select it from the List of Values. Note: You can only enter a value in this field if the order code 6 (External Service Order) has been selected in the header.
  5. The full name of the external service type appears automatically in the Service Description field.
  6. In the Quantity field, indicate the number of parts to be sent out for external service.
  7. In the Serial No field, enter the serial number of the part to be sent out for external service if it is serial tracked. Note: You can only enter a value in this field if the order code 6 (External Service Order) has been selected in the header.
  8. In the Lot Batch No field, enter the lot/batch number of the part to be sent out for external service if it is lot/batch tracked. Note: You can only enter a value in this field if the order code 6 (External Service Order) has been selected in the header.
  9. In the Wanted Receipt Date field, indicate the date by which the part needs to be received back at site.
  10. In the Supplier field, the supplier who is defined as the primary supplier of this part appears automatically. You can change the supplier by using the List of Values if several suppliers are defined for the part. If a supplier is not connected to the part, right-click and then click Supplier for Part, and then enter a supplier for the part.
  11. Save the record.

Optional steps (remember to save your entries):

Note: If you enter additional cost amounts directly on the Additional Cost or Additional Cost Gross/Curr field, you will not be allowed to enter additional cost details using additional cost types via the right-mouse button menu.