Assigning budget/forecast estimate to complete values is a process where you
start with a budget on one particular level and assign it to another level or
move it between the branches of a structure. This helps to make sure that
control and comparison is made at the correct level, where the actual values
appear. Using the Assign ETC function ensures that changes made are done in a
controlled manor and with the possibility of adding notes to every move.
If multicurrency budgeting and forecasting and/or project currency is used it is
possible to change the currency code between the source and the destination
lines. In this case the changes needs to be validated against either the Base
B&F Currency or the Project Currency. The validation rule can be set up in the
Project/Currency tab.