Perform this activity to add resource(s) to an activity. The main purpose of
this is to control who will work on a certain activity and how much work is to be
done, with more detail. The values given here will be used for performing an approximate
capacity planning across one or more projects.
You can assign several resources to one activity. It is important that the resources
you connect have cost and capacity defined for the right period according to your
project. The resource cost and capacity to use is defined by the activity's early
start and finish dates. The cost and hours for the resources will be reported to
the project according to the project cost elements you have defined for the resource.
Project Navigator/Resource
Activity/Resource/Resource
Planning
Activity Resources
Project Navigator/Resource
Activity/Resource/Resource Planning
Activity
Resources
Note that the above procedure can also be done in the Activity/Resource/Resource Planning tab.