Perform this activity to connect existing objects to a project activity, such as a Material Requisition line, Purchase Requisition Part line, Purchase Requisition No Part Line, Purchase Order Part line, Purchase Order No Part Line, Customer Order line, Shop Order, DOP Header or a Design object.
The material requisition line must have the Planned or Released status.
The material requisition line must not be connected to a project activity.
The material requisition line must not have the Purchase Order supply code.
The purchase requisition line must not have PO Created status.
The purchase requisition line must not be connected to a project activity.
The purchase requisition line must have demand code Inventory Order or Non Inventory (for non-inventory parts and no-parts)
The purchase requisition line shall not have any exchange components.
The purchase order line must have the Released, Stopped or Confirmed status.
The purchase order line must have demand code Inventory Order or Non Inventory (for non-inventory parts and no-parts).
The purchase order line must not be connected to a project activity.
The purchase order line must not be manually pegged to a customer order line or a shop order material line.
The purchase order line shall not have any exchange components.
The customer order line must have the Released status.
The customer order line must have the Invent Order, Pkg, Non Inventory, Purch Order Trans, Int Purch Tran, Purch Order Direct, Int Purch Direct, Shop Order, Dop Order or Not Decided supply code.
The customer order line must not be connected to a project activity
The customer order line must not be manually pegged to a purchase order line or a shop order.
The customer order line must not be a customer consignment stock delivery.
If the customer order head is connected to a project it is not allowed to connect any customer order line to another project.
Only Shop Orders in the Planned status can be connected to an activity.
The shop order can not be connected to several activities - it's only possible to connect a shop order to one activity.
The shop order must have demand code Inventory Order, in other words only ordinary shop orders and repair shop orders can be connected. Any MRO-related shop orders like assembly, disassembly or disposition shop orders can not be connected manually to the activity.
Only DOP Headers in status Created can be connected to an activity.
The DOP Header can not be connected to several activities - it's only possible to connect a DOP Header to one activity.
It shouldn't be possible to connect a DOP Header that's connected/created as a job (attribute Financial Integration should be No Integration), against an activity.
N/A