Connect or Register Work Order

Explanation

Work Orders and Routes registered in IFS/Service Management can be connected to project activities. It is also possible to create new Active Work Orders, which are automatically connected to the project activity. 

Prerequisites

System Effects

Window

Project Navigator/Connections

Activity/Connections

Project Navigator/Work Orders/Active Work Orders

Activity/Work Orders/Active Work Orders

Active Work Orders

Prepare Work Order

Report In Work Order

Active Routes

Report In Route

Related Window Descriptions

Project Navigator/Connections

Project Navigator/Work Orders/Active Work Orders

Procedure

Project Navigator/Connections
Activity/Connections

  1. Select the required activity.
  2. Select the menu option Connect/Disconnect Object.
  3. In the Connect/Disconnect Object dialog box select the Active Separate Work Order tab or Active Round Work Order tab.
  4. Select the work orders to be connected to the activity.
  5. Click OK to save the changes then close the dialog box.

Project Navigator/Work Orders/Active Work Order

Activity/Work Orders/Active Work Order

  1. Select the required activity.
  2. Create a new record in the Active Work Order tab.
  3. Enter or select from the List of Values a WO Site and a Maintenance Organization.
  4. Enter a suitable Directive.
  5. Save the changes.