Connect Cost Breakdown Structure to Project

Explanation

The cost breakdown structures that belong to a company can be connected to projects in the same company. Once connected a structure can be used to plan project budgeting and forecasting.

Prerequisites

System Effects

Window

Project Details
Project Cost Breakdown Structure

Related Window Descriptions

Project Details
Project Cost Breakdown Structure

Procedure

From the Project Details window

  1. Open the Project Details window and query for your project.
  2. Enter the relevant structure ID in the CBS ID field. The List of Values will show the structured available for the company.
  3. Click Save.

From the Project Cost Breakdown Structure window

  1. Open the Project Cost Breakdown Structure window and query for the relevant structure ID.
  2. Enter the relevant project ID in the Project ID field. The List of Values will show the projects available for the company.
  3. Click Save.