Define Project Demand Miscellaneous Part Cost Details
Explanation
This activity is used to add or modify details on the planned cost or hours of
a miscellaneous part in a project demand.
Prerequisites
- A miscellaneous part must be defined on a project.
- Project Cost Elements must be defined in Accounting Rules.
System Effects
- You can define cost elements which can be used for planning on project miscellaneous
demand
records.
Window
Project Navigator
Project
Related Window Descriptions
Planned Cost/Hours per Cost
Element
Procedure
- Open the
Project
Navigator or the Project
window, and query for the project for which cost or hours on misc. parts
needs to be defined.
- Click on the Demand/Misc. Parts tab, select a misc. part line, right click and then click
the Cost Elements menu option. The Planned Cost/Hours per Cost Elements dialog box
will open.
- Click on a row in the table, and click on the New button.
- Enter a cost element in the Cost Element field, to which planned
cost or hours needs to be entered. You can use the List button to
select from a list of project cost elements as well.
- In the Planned Cost field, enter the cost for the relevant cost element
and misc. part.
- In the Planned Hours field, enter the hours
for the relevant cost element and misc. part.
- Click Apply.