Insert Project Milestones

Explanation

Project milestones specify one or several dates for planned revenues in the project. Examples of project milestones are: first payment when the specification is finished, next payment when the prototype is finished, and final payment when the product is delivered. We then have the following project milestones defining the milestone identification, milestone date, description, and planned revenue:

Prerequisites

System Effects

Window

Project/Milestones

Related Window Descriptions

Project/Milestones

Procedure

  1. Create a new milestone in the table.
  2. Enter a milestone ID, milestone date, description, and planned revenue.
  3. Repeat steps 1 and 2 for each milestone to be registered.
  4. Save the project milestones.