Modify Requested Date
Explanation
The required date is set to
the early finish date for the activity. If this date is changed, select the menu
option Modify Requested Date to reflect the date change in its connected
supply.
In Project Delivery, the
required date is set to the early finish date of the activity which has been
connected to the project specific item. If this date has been changed or the project item has been connected to another activity,
then a new Gross Requirements Calculation (GRC) must be run in order to reflect
the new required date for the project specific item in the MPL. If a supply
request has already been created for it, the Modify Requested Date menu
option can
be selected to change the required date of the existing supply.
Prerequisites
- The requested date must be different from the required date.
- A DOP Header in which is either in the Created, Unreleased or Released
status must have been created
for the miscellaneous part, and if it is in Project Delivery it should be
created for the project item.
- A Shop Order in either the Planned, Released, Reserved or Started status
must have been created for the miscellaneous part, and in Project Delivery
it should be created for the project item.
- The Purchase Requisition line must be in either
the Planned or Released status. If a Purchase Order had been created from the Purchase
Requisition, the Purchase Order must be in either the Planned, Released or
Confirmed status. If execution of the change management functionality in
IFS/Purchasing require that a Purchase Order Change Order should be used to
handle changes in a Released Purchase Order, a Purchase Order Change Order
must exist in Planned status.
- Changes must have been done in the early finish date on the connected activity, or the
part has been connected to another activity.
System Effects
- The Due Date
on the DOP Header is updated according to the Required Date on the project
demand line.
- The Need Date on the Shop Order is updated according to
the Required Date on the project demand line.
- The Wanted Receipt Date on the Purchase Requisition line
or the Planned Receipt Date on the Purchase Order or
the Purchase Order Change Order line is updated according to
the Required Date on the project demand line.
- The Requested Date is updated according to the Required
Date on the project demand line.
Window
Project
Navigator/Demand/Misc.
Parts
Project/Demand/Misc.
Parts
Project
Product/Demand/Misc. Parts
Project
Navigator/Demand/Misc.
No Parts
Project/Demand/Misc.
No Parts
Project
Product/Demand/Misc. No Parts
Project
Product/Supply/Procured
Project
Navigator/Supply/Procured
Projects/Supply/Procured
Related Window Descriptions
Project
Navigator/Demand/Misc. Parts
Project/Demand/Misc.
Parts
Project
Product/Demand/Misc. Parts
Project
Navigator/Demand/Misc.
No Parts
Project/Demand/Misc.
No Parts
Project
Product/Demand/Misc. No Parts
Project Navigator/Supply/Procured
Projects/Supply/Procured
Project Details/Supply/Procured
Project
Product/Supply/Procured
Part
Procurement Info/Procured
Procedure
- Select the miscellaneous demand line or the project
item.
- Select the Modify Requested Date right mouse
button menu option.