When an activity is in Completed status, it can be returned to Released status via the menu option Reopen. Similarly when an activity is in Closed status, it can be returned to Completed status via the menu option Reopen. This enables additional, perhaps overlooked, work to be reported before the activity is set to Completed or Closed again.
Activities
Project Navigator/Activity
List
Project Navigator/Activity
Activities
Project Navigator/Activity
List
Project Navigator/Activity
Select the activity to be reopened, then select ReOpen option in the menu.