Reopen Activity

Explanation

When an activity is in Completed status, it can be returned to Released status via the menu option Reopen. Similarly when an activity is in Closed status, it can be returned to Completed status via the menu option Reopen. This enables additional, perhaps overlooked, work to be reported before the activity is set to Completed or Closed again.

Prerequisites

System Effects

Window

Activities
Project Navigator/
Activity List
Project Navigator/Activity

Related Window Descriptions

Activities
Project Navigator/Activity List
Project Navigator/Activity

Procedure

Select the activity to be reopened, then select ReOpen option in the menu.