Register Project Demand

Explanation

Perform this activity to define the parts and services (no parts) needed by the project.

There are four supply options available for a part: Purchase, Shop Order, Dynamic Order Processing (DOP) and Project MRP. A default value is given depending on the part type and supply type in inventory.

When the part has the Project MRP supply option, then a supply will be generated by Project MRP , if there are no pegged supplies that have been already created.

If the part is a standard planned item, the demand for it will be seen by MRP and Order Point calculations. The Create Project Supply Request menu option is also disabled in this case. Reservation and issues of standard planned items are done from standard inventory. Committed cost is acquired when the part is reserved, while used cost and progress are acquired when the part has been issued. If the part is project specific, then reservation is done from project inventory.

A service (no part) has no supply option to select from. It can only be purchased by default.

An offset can be given to a miscellaneous demand line. An offset is a number of days which the early finish date can be adjusted with to give the desired required date. If not specified, the required date for a miscellaneous demand will be the same as the early finish date of the connected activity.

Prerequisites

System Effects

Window

Project navigator/Demand/Misc. Parts

Activity/Demand/Misc. Parts

Project/Demand/Misc. Parts

Project Navigator/Demand/Misc. No Parts

Activity/Demand/Misc. No Parts

Project/Demand/Misc. No Parts

 

Related Window Descriptions

Project Navigator/Demand/Misc. Parts

Project Navigator/Demand/Misc. No Parts

Procedure

From the Project Navigator/Demand tab and Activity/Demand tab

  1. Enter the part and required quantity to procure.
  2. If you want to add hours for the cost elements, right click on the relevant part and select the Cost Elements menu option.
  3. Enter the planned hours for the relevant cost element in the Planned Cost/Hours per Cost Element dialog box.
  4. Click OK.
  5. Enter an offset if desired.
  6. Save.

From the Project/Demand tab

  1. Enter the relevant activity sequence, the Part (or No Part) and required quantity to procure.
  2. If you want to add hours for the cost elements, right click on the relevant part and select the Cost Elements menu option.
  3. Enter the planned hours for the relevant cost element in the Planned Cost/Hours per Cost Element dialog box.
  4. Click OK.
  5. Enter an offset if desired.
  6. Save.