Resolve Project Currency Errors

Explanation

If multicurrency budgeting and forecasting or project currency is used sometimes errors occur if the currency code on the activity connected object is not present in the currency rate types used for budgeting and forecasting which is specified in Project Details/Currency tab. In this case calculations can not be performed for the currencies Base Currency at B&F Rate and/or Project Currency. By adding the missing currency code to the relevant rate types the errors can be corrected.

Prerequisites

System Effects

Window

Project Currency Errors

Related Window Descriptions

Resolve Project Currency Errors

Procedure

  1. Open the Resolve Project Currency Errors window, and query for the company and project on which the corrections should be done.
  2. Click OK.