Project Miscellaneous Demand
Material and services are procured by the project through project miscellaneous demand. The demand for material and/or service is entered at project activity level.
A material or part can either be standard or project-specific. If the part is a standard planned item, the demand for it will be seen by standard MRP and Order Point calculations. The part can also be reserved or issued from standard inventory if there is quantity available.
For a project-specific item, the material reservation and issuing are done from project inventory. A project "owns" its project inventory, ensuring that material acquired to this project cannot be issued to fulfill other demands, either from another project or from non-project related demands. No further costs are added and fed back to the project when issuing from the project inventory since the project has already taken the cost when the material was received into the project inventory.
Demand for inventory parts and non-inventory (purchase) parts is entered in the Misc. Parts tab. Given the supply option, Part Type and Default Supply Type in inventory, an appropriate supply will be created for the part if it is project-specific.
There are four available supply options: Purchase, Shop Order, Dynamic Order Processing and Project MRP. If the part has the supply option Purchase or Shop Order, then a Purchase Requisition or Shop Order is created respectively, otherwise a DOP Header if Dynamic Order Processing (DOP) has been selected. However, if Project MRP has been selected, then a supply request is created by Project MRP when it is performed. Refer to activity Perform MRP in Manufacturing/Make to Stock Planning for detailed information.Cost and progress are fed back to the project activity when the part is reserved (committed cost), or issued (used cost and progress). The part can be reserved and issued either from inventory or from the created supply request.
Demand for a service (no part) is entered in the Misc. No Parts tab. A service has no supply option to select from. It can only be purchased by default.The main flow is as follows:
Register the demand in either the Misc. Parts or Misc. No Parts tab.
Net the demand from standard or project inventory, if there is any quantity available.
Create a supply request for the demand through the menu option Create Project Supply Request. If a Purchase Requisition has been created, convert it to a Purchase Order, then process and receive it. Process the Shop Order or DOP Header if that supply request has been created instead.
Reserve the part through menu option Reserve. Note that the quantity of a part is reserved automatically when the supply request is received, e.g., if the Purchase Order has been received.
Create and print a pick list for the selected miscellaneous demand lines.
Issue the part through the menu option Issue. Note that issuing (and reservation) of parts from inventory can also be done manually.
Monitor the cost and progress of the created supply request on the connected project activity.