Run Gross Requirement Calculation
Explanation
Use the Calculate Gross Requirements menu option to perform the gross
requirement
calculation, which analyzes the item structure and determines when the items must be
available to be able to assemble the project product delivery structure. All items without
an activity belong to the activity registered on the nearest item upward in the structure.
Items in substructures of standard planned items, project MRP supplied items, or
items that do not belong to any structure are not included in the calculation. Items in substructures of
standard planned items or items not belonging to any structure are not included
in the calculation. It is recommended that you run the Warning Info menu
option before you start the
calculation. If you run the calculation in batch mode, it is executed as a
background process. The status of the background job can be viewed by selecting Background
Jobs in the General folder of the IFS Navigator. Parts with the Part Status flag in
inventory set to Demand Not Allowed will never be calculated.
Prerequisites
- The correct MPL part code must be used on the project items and
the standard parts in IFS/PDM Configuration. See MPL Part in
Project
Product/items.
- The item you want to calculate must have a structure, and at
least one item must be connected to an activity. See
Project Product/Requirement
Activities.
- A top item must have been entered for the delivery project
in Delivery Projects.
System Effects
- The result of the previous gross requirement calculation is removed.
- A new procurement list is generated, starting with the project top item and then moving
down in the structure until an Mp-demand item is found. For each item, the following
checks and calculations take place:
- The total quantity for each item is calculated (item quantity multiplied by
the quantity of the parent item).
- The demand date is set for each item based on the early finish date of the nearest
connected activity upwards in the structure and the lead time in workdays for each
part/item on the different levels accumulated. The lead time is fetched from the
inventory
part on the project delivery site, or from the engineering part if the inventory part lead time returns 0
(zero). The project's calendar is also taken into consideration when
calculating the demand date.
- If an item does not have an activity connected and none of its ancestors has an
activity, a warning is given and is indicated by the MPL calculation flag.
- The result of the calculation is inserted into the material procurement
list for all
items with the acquisition code set to Procurement.
Window
Project
Product
Related Window Descriptions
Project Product/Demand/MPL
Procedure
- Open the Project Product
window and
query for project for which you want to run the gross requirement calculation.
- It is recommended to view the Warning Info window prior to the
calculation to get an overview of items with missing activities and items
that are not going to be procured with the current settings. Use the Warnings
menu option.
- Open the Project Product/Demand/MPL
tab and select the Calculate Gross Requirements menu option to start the calculation. If you
want to run the calculation in the background, select the Run the Procedure in Batch Mode
check box.
- Click OK.