Enter Analysis Results for Production Schedule Parts
Explanation
Use this activity to enter analysis results for one or more analyses connected to a production schedule. This
optional task is to be performed by a system administrator or equivalent person.
This activity allows you to record the measure quality results against the
quality test plan (analysis type) on completion of a producion schedule.
Specific quality test results for a part within a manufacturing cell are
recorded. The analysis must first be created during the production schedule
receipt process.
You can change the status of an analysis to Complete. Only results in
complete status are considered when creating control charts or calculating capability indices.
Once the line has this status, the results cannot be edited. You can also create a new control chart
if SPC is
activated in the control plan.
When all
test operations have been reported, you can confirm the status for one or
more analyses.
Once an analysis has been confirmed, the results cannot be edited.
Prerequisites
This activity has the following prerequisites:
- This activity requires analyses to have been created in the
Production
Schedule by Line,
Production Schedule by Line Part,
Production
Receipt, or
Report Point
Receipt window.
- To be able to enter analysis results, an analysis
must exist in the Planned status.
System Effects
As a result of this activity:
- Results are entered for created analyses.
- Results can be used in the creation of various IFS/Quality Management charts.
Window
Analysis
Results
Overview Production Schedule Analysis
Related Window Descriptions
Analysis Results
Production Schedule Analysis
Create Analysis
Production Schedule
Analysis
Procedure
To perform this activity, follow these steps:
- If you are working on previously created analyses, open the
Analysis Results window and query for the part
for which you want to enter data.
- If you just created the analyses, the system prompts you to indicate
whether you want to view the created analysis overview. If you click Yes,
the Overview Production Schedule Analysis window appears. Right-click on the line for which you want to report results and
then click Analysis Result to open the
Analysis Result window.
- Select the
line for which you want to report results.
- If the data type is Attribute, enter your results in the Noncomformities (c/u) and/or
the Noncomforming (np,p) fields in the table.
- If the data type is Variable, enter your results in the Result field in the
by entering as
many measurement values as the specified sample size.
- Save the changes.
- To change the status to Complete, right-click and then click Complete
Registered Results.
- To create a new control chart if SPC is activated in the control plan,
right-click on the line and click Create SPC Chart.
- To print a test instruction, right-click in the header and then click
Print Test Instruction. The test instruction includes all control plan
lines.
- To add document text to any line, right-click and click Document Text.
- To print a report of your results for any line, right-click and click
Print Data Sheet.
- To confirm a single analysis, right-click in the header of the analysis
and then click Confirm Registered Results.
- When the analysis results are confirmed, the values
in the Variable Result Status and Attribute Result Status
fields are calculated automatically.
- To confirm multiple analyses, select one or more analysis in the
Analysis window, and then right-click and click Confirm Registered
Results.