Define Resource Capacity
Explanation
Use this activity to define the capacity for a resource.
Prerequisites
A resource must exist.
System Effects
As a result of this activity, capacity is defined for the resource.
Related Window Descriptions
Simulation
Define Resource Structure
Procedure
- In the Simulation window,
right-click and then click View Resource
Structure. The Resource Structure window opens.
- Click the required resource in the explorer.
- Right-click on the data grid and
click Insert.
- In the Begin Date field and the End Date field, enter the
relevant dates.
- In the Enter Capacity Hours per Workday field or Capacity FTE per Workday
field, enter applicable values.
- Save.