Define Resource Capacity

Explanation

Use this activity to define the capacity for a resource.

Prerequisites

A resource must exist.

System Effects

As a result of this activity, capacity is defined for the resource.

Related Window Descriptions

Simulation
Define Resource Structure

Procedure

  1. In the Simulation window, right-click and then click View Resource Structure. The Resource Structure window opens.
  2. Click the required resource in the explorer.
  3. Right-click on the data grid and click Insert.
  4. In the Begin Date field and the End Date field, enter the relevant dates.
  5. In the Enter Capacity Hours per Workday field or Capacity FTE per Workday field, enter applicable values.
  6. Save.