Add Sub Contract Approval
Explanation
This activity is used to add an approval to the sub contract. In several 
stages of the sub contract it needs an approval process to proceed. For example, 
when releasing a sub contract, the Contract Manager may be required to approve 
the scope of the contract created. Or when awarding the sub contract, again it 
may need approval. Since the same approval routing can be used in several stages 
of the sub contract, the required approvals can be defined initially when 
creating the sub contract, and will be triggered in the event of a status change 
on the sub contract.  
Prerequisites
  - A sub contract  must exist. 
- If an approval routing is to be added, IFS/Document Management must be installed.
System Effects
  - An approval is added to the sub contract.
Window
Sub Contract
Related Window Descriptions
Sub Contract/Approvals
Procedure
  - Open theSub Contract window and query (F3) for the necessary sub contract.
- Click the Approvals tab and create a new record (F5).
- Enter an Approval ID, Approval Description and Contract 
	Approved Status.
- Save the information (F12).
- Repeat these steps for each approval that needs to be created.