Finalize Contractual Commitments
Explanation
This activity is used to finalize contractual commitments. This is a manual 
operation. However, if valuations are used, retentions need to be considered as 
follows:
  - On completion of the sub contract, a final retention period, 
where any faults may be reported for correction, is usually agreed upon.
- Once this retention period expires, the retention 
amount must be paid out.
- Any interim retention should also be released at this 
point, unless the supplier has released it at an earlier date.
Prerequisites
N/A
System Effects
N/A
Window
Sub Contract
Related Window Descriptions
Sub Contract
Procedure
This is  a manual operation.