Modify Sub Contract Line Item
Explanation
This activity is used to update sub contract line items. Some values have 
dependencies on other contract values, and validations will be performed to ensure that all 
combinations are valid. For more information, refer the activity Add Sub Contract Line Item.
If Application For Payment is used, and there exists a valuation in the Planned 
status, you are recommended to refresh the valuation with the latest sub contract 
information. For more information, refer the activity
Refresh Sub Contract Details on 
Valuation.
Note:
A warning message will be displayed if there is a valuation against the sub 
contract, and the value of the line item on the sub contract is changed so that 
it is less than the value of the valuation.
Prerequisites
  - The sub contract should not be any of the following statuses: Completed, 
	Closed or Cancelled.
- The sub contract revision should not be in any of the following statuses:
	Approval In Progress, Obsolete 
  or  Cancelled.
- The sub contract revision must not be Frozen.
- The sub contract line item should be in either the Planned or Work In Progress 
	status.
- If the check boxes Audit Trail Enabled, Variation Order and/or 
	Variation Comment Required is selected, you need to enter a variation order number and/or variation comment to 
  be able to save the change(s).
System Effects
  - The sub contract line item is modified.
- If the contract revision has the Audit Trail Enabled check box selected:
    - The Change Status field on the line item is set to Changed.
- The old values of the changed line are logged in the 
	Change History tab together with any variation order 
    number and variation order comment entered.
 
- Any variation order number and variation order comment is added to the modified 
  sub contract line item.
Window
Sub Contract
Related Window Descriptions
Sub 
Contract/Items/Lines/Items
Procedure
  - Open the 
	Sub Contract window and query (F3) for the 
	necessary sub contract.
- Click the 
	Items tab and then click the 
	Lines/Items 
	sub-tab.
- Select the line item and modify the data, as required.
- Save the information (F12).