Submit Invitation to Tender
Explanation
This activity is used to submit an invitation to tender to the supplier(s). Invitations to 
tender can be sent to several different suppliers for the same contract. Therefore, it is necessary to be able to keep track of all 
the invitations to tender 
during the planning, releasing and submitting phases of a sub 
contract.
Prerequisites
  - A supplier must exist on the sub contract.
- The sub contract  must be in any of the following statuses: Planned, 
	Released or Submitted.
System Effects
  - An invitation to tender is submitted to one or more suppliers on the sub contract.
Window
Sub Contract
Sub Contracts
Related Window Descriptions
Sub Contract 
Sub Contract/Supplier 
Sub Contracts
Procedure
Option 1:
	- Open the 
	Sub Contract window or the 
	Sub Contracts window.
- Query (F3) for the necessary sub contract.
- Right-click anywhere in the header, point to Status, and then 
	click Submit Invitation. The 
	Submit Invitation to Tender 
	dialog box opens.
- In the Supplier ID field, enter the supplier. Click List 
	to select a valid value.
- Click OK.
Option 2:
	- Open the 
	Sub Contract window and query (F3) for the 
	necessary sub contract.
- Click the 
	Supplier tab.
- Select the supplier, right-click, and then click Submit Invitation. 
	The 
	Submit Invitation to Tender dialog box opens.
- Click OK.