Creating Plan Structure—Exercises
IMPORTANT |
It is extremely important that you set up and work within your own
site to maintain your data integrity. If you work within any other
site, you will compromise your own exercise data as well as the data of
other students. Predictable exercise results require that your data
be isolated in your own site. |
Required Data
Entering Inventory Part
Purpose: The purpose of this exercise is to show you how to
set
up the basic data required for running this particular functionality.
Windows:
Copy Parts to Site
Inventory Part
Note: If you already have the racing engine parts in your site
as shown in the table below, use
your existing parts. These parts all have part numbers with the format 20-nnn.
- Copy all parts from Site 1 to your site using 200 as the value for
Commodity Group 2.
- Save your changes.
Part No |
Part Description |
Planner |
Planning Method |
20–000 |
Engine Family |
Niki |
O |
20–101 |
Formula Engine |
Niki |
T |
20–102 |
Stock Engine |
Niki |
T |
20–106 |
6-Cylinder Engine |
Niki |
A |
20–108 |
8-Cylinder Engine |
Niki |
A |
20–104 |
4-Cylinder Engine |
Niki |
A |
20–105 |
5-Cylinder |
Niki |
A |
General exercise for Creating
Manufactured Inventory Part
General exercise for Copying
Parts to Site
Main Exercises
Purpose: Purpose: The purpose of this exercise is to familiarize you with the functionality
for entering a planning structure for
a master scheduling family.
Windows:
Plan
Structure
- Open the
Plan Structure window.
- Query for Part 20–000 on your site.
- On the
Planning Structure tab, create a new row.
- Enter the component parts (green boxes) in the Component Part column
as shown in the
chart below and site in Component Site column (use your own site). Optionally
you can enter your own site first in Component Site column to be able
to use List of Values for Component Part.
- In the Quantity per Assembly column, the
product mix is entered, i.e., the percentage expressed as a decimal, where
1.0 equals 100%.

- Save your changes.
- In the Status field, change the status to Plannable using the right-clicking option. You have now entered a master scheduling family
that is equal to the part for Level 0.
- Open the
Plan Structure window.
- Query for Part 20–000 on your site.
- Select the manufactured part, right-click, and then click Next Level
to move to the next level.
- Enter the component parts (blue boxes) in the Component Part field
as shown in the diagram above.
- In the Quantity per Assembly field, enter the
product mix. This value is a percentage expressed as a decimal, where 1.0
represents 100%.
- Save your changes.
- In the Status field, change the status to Plannable.
- Go to Line Item No 1
, right-click, and then click Previous Level to move to the next higher
level.
You have now entered a complete planning structure that ends at
MS Level 1 equals end items, product structure parts, recipe structure parts, or