Closing Shop Orders—Extended Exercises
IMPORTANT |
It is extremely important
that you set up and work within your own site to maintain your
data integrity. If you work within any other site, you will
compromise your own exercise data as well as the data of other
students. Predictable exercise results require that your data
be isolated in your own site. |
Basic Data Setup
Discrete Manufacturing Overview Racing Engine
Purpose: The purpose of this exercise is to create the required data that
will be used in the Discrete Manufacturing exercises. This sets up data for your site that only
needs to be done once for Discrete Manufacturing course exercises.
- Set up your site for discrete manufacturing of racing engines.
General exercise for
Overview of Discrete Manufacturing Data
Inventory Location
Purpose: The purpose of this exercise is to set up an
inventory picking location for running functionality isolated by site.
Windows:
Inventory Locations
- If you haven't done so already, create the inventory picking location
shown in the table
below.
Site |
Location No |
Warehouse |
Location Name |
Location Group |
Your Site |
2C |
Sub |
Subassembly inv |
30 |
General exercise for
Entering Inventory Locations
Required Data
Inventory Part Balance
Purpose: The purpose of this exercise is to verify that
you have enough parts to complete the main exercises.
Windows:
Inventory Part Currently On Hand
Receive Inventory Part
- Verify that you have at least the quantity of parts shown on the table
below available for manufacturing. If you do not, receive the indicated quantity of the parts into
inventory picking locations.
Site |
Part Number |
Part Description |
Quantity Available for Manufacturing |
Your Site |
21-330 |
Ignition System |
10 |
Your Site |
21-331 |
Starting System |
10 |
Your Site |
21-332 |
Battery System |
10 |
Your Site |
21-930 |
Sheet Steel, .5 cm |
30 |
General exercise for
Receiving
Inventory Part
Shop Orders
Purpose: The purpose of this exercise is to create the shop orders
that will be used in the
main exercises below
Note: These shop orders will need to be processed to specific
states for the exercises.
- Create shop orders for the parts and quantities shown in the table below.
- Record the shop order numbers so that it will be
easy to identify the correct shop order for each main exercise.
Site |
Part Number |
Part Description |
Lot Size |
Shop Order Number |
Relevant Exercise |
Your Site |
21-230 |
Electrical System |
10 |
|
Receive and Auto-Close Shop Order |
Your Site |
21-313 |
Oil Pan |
10 |
|
Receive and Manually Close Shop Order |
General
exercise for Creating Shop Orders Manually
Main Exercises
Purpose: The purpose of these exercises is to close shop orders
by closing them manually and closing them with the auto-close process.
Windows:
Shop Order
There is one shop order for electrical systems and one shop order for oil
pans. You want to:
- Set the close tolerance to 10% for a shop order for 10 electrical systems. You
want the shop order to close automatically when the receipt of material is
within the close tolerance.
You want to set the close tolerance to 10% for a shop order for 10 electrical systems. You
want the shop order to close automatically when the receipt of material is
within the close tolerance.
- Open the
Shop Order window and query for the shop order for
this exercise. If you did not record
the shop order number, query for your site, part number 21-230 and a quantity
of 10. If the shop order is not released, release it.
- Right-click anywhere in the header, point to Material Actions, and
then click
Reserve to reserve the material for your shop order.
- Click the
Detail tab. Verify the value in the Tolerance
field (in the Auto Close area). Also verify that Auto Close is
selected from the Code list.
Note: If you have specified a value in the Close Tolerance field of the
Inventory
Part/Manufacturing tab, it will be displayed in the Tolerance
field of the relevant shop orderby default.
- Change the Tolerance field value to 10. This will allow the shop
order to automatically close if it receives at least 9 electrical systems
(10 - 1).
- Right-click anywhere in the header, point to Material Actions, and
then click
Manual Receive.
- When the
Receive Shop Order window displays, select the Receive
With Backflush check box. Also select the Auto Report Of Operations check box.
- On the
Inventory Receipt tab (in the
Receive Shop
Order window), check for a record for location 2C. If a record for location 2C does not
appear, create a
new record, entering 2C in the Location
No field. If there is already such a record, use it.
- In the Quantity Received field, enter 8.
- Save the information.
- Close the
Receive Shop Order window.
- Refresh the
Shop Order window.
- Verify that the state in the header has changed to Started.
- On the
Detail tab, verify that the Qty Complete
field now displays 8 and that the value in the Products
field has changed to Partially Received. In the State area, verify that the value of
the Material
field is Partially Issued, and the value of the Operations field is Partially Reported.
The shop order did not close automatically because the material reported
complete was not within the close tolerance.
- Right-click anywhere in the header, point to Material Actions, and click
Manual Receive.
- When the
Receive Shop Order window displays, select the Receive
With Backflush check box. Also select the Auto Report Of Operations check box.
- On the
Inventory Receipt tab (in the
Receive Shop
Order window), enter 1 in the Quantity Received field.
- Save the information.
- Close the
Receive Shop Order window.
- Refresh the
Shop Order window.
- Verify that the state in the header has changed to Closed.
- On the
Detail tab, verify that the Qty Complete
field now displays 9 and that the value in the Products
field has changed to Partially Received. In the State area, verify that the value of
the Material
field is Completely Issued, and the value of the Operations field is
Completely Reported. The shop order closed automatically because the
material reported complete was within the close tolerance.
- You decide that you want to reopen the shop order and receive the last
electrical system. Right-click anywhere in the header, and then click Open.
Verify that the state in the header has changed to Started.
- Click the
Material tab. Verify that the value in the Qty
Required field for each row had changed to 9 when the shop order was
automatically closed. Change the value to 10 in the Qty Required
field for each row. Save the information.
- Right-click anywhere in the header, point to Material Actions, and
then click
Manual Receive.
- When the
Receive Shop Order window displays, select both the Receive
With Backflush check box and the Auto Report Of Operations check box.
- On the
Inventory Receipt tab (in the
Receive Shop
Order window), enter 1 in the Quantity Received field.
- Save the information.
- Close the
Receive Shop Order window.
- Refresh the
Shop Order window.
- Verify that the state in the header has changed to Closed.
- On the
Detail tab, verify that the Qty Complete
field now displays 10 and that the value in the Products
field has changed to Completely Received. In the State area, verify that the value of
the Material
field is Completely Issued, and the value of the Operations field is
Completely Reported. The shop order closed automatically because the
material reported complete was within the close tolerance.
- Close the
Shop Order window.
You want to set the close tolerance to 10% for a shop order for 10 oil pans. You
also decide that you want to close the shop order manually after 11 oil pans have been received.
- Open the
Shop Order window and query for the shop order for
this exercise. If you did not record
the shop order number, query for your site, part number 21-313 and a quantity
of 10. If the shop order is not released, release it.
- Right-click anywhere in the header, point to Material Actions, and
then click
Reserve to reserve the material for your shop order.
- Click the
Detail tab. Verify that the value in the Tolerance
field (in the Auto Close area) is 0. Verify that Auto Close is
selected from the Code list.
- Change the Tolerance field value to 10. This would allow the shop
order to automatically close if it received at least 9 electrical systems
(10 - 1).
- In the Code list in the Auto Close area, click Manually
Close so that the shop order will not close automatically when the close
tolerance has been satisfied.
- Save the information.
- Right-click anywhere in the header, point to Material Actions, and
then click
Manual Receive.
- When the
Receive Shop Order window displays, select both the Receive
With Backflush check box and the Auto Report Of Operations check box.
- On the
Inventory Receipt tab (in the
Receive Shop
Order window), check for a record for location 2C. If a record for location 2C does not
appear, create a
new record, entering 2C in the Location
No field. If there is already such a record, use it.
- In the Quantity Received field, enter 8.
- Save the information.
- Close the
Receive Shop Order window.
- Refresh the
Shop Order window.
- Verify that the state in the header has changed to Started.
- On the
Detail tab, verify that the Qty Complete
field now displays 8 and that the value in the Products
field has changed to Partially Received.
- Right-click anywhere in the header, and then click Close. When the
Close Shop Order
window displays, click OK
without changing the values in any
fields.
- Click OK to acknowledge the message that the shop order cannot
close because the product is not within the close tolerance.
- Right-click anywhere in the header, point to Material Actions, and
then click
Manual Receive.
- When the
Receive Shop Order window displays, select both the Receive
With Backflush check box and the Auto Report Of Operations check box.
- On the
Inventory Receipt tab (in the
Receive Shop
Order window), enter 1 in the Quantity Received field.
- Save the information.
- Close the
Receive Shop Order window.
- Refresh the
Shop Order window.
- Verify that the state in the header is still Started.
- On the
Detail tab, verify that the Qty Complete
field now displays 9 and that the value in the Products
field has is still Partially Received.
- Right-click anywhere in the header, and then click Close. When the
Close Shop Order
window displays, click OK
without changing the values in any
fields.
- Click OK to acknowledge the message that the shop order cannot
close because the product is not within the close tolerance. This is because
none of the by-products has been received.
- Right-click anywhere in the header, point to Material Actions, and
then click
Manual Receive.
- When the
Receive Shop Order window displays, in the Received Part area,
verify that the list displays Shop Order, the Remaining
Qty field has the value 1 and the other two fields show part number
21-313 and Oil Pan. These fields represent the part to be received. In the
list, click Byproduct. Verify that the values of the other fields in
the Received Part area change to the information for part 21-935
(Steel, Scrap).
- On the
Inventory Receipt tab (in the
Receive Shop
Order window), check for a record for location 2C. If a record for location 2C does not
appear, create a
new record, entering 2C in the Location
No field. If there is already such a record, use it.
- In the Quantity Received field, enter 4.5.
- Save the information.
- In the list under Received Part (of the
Receive Shop Order
window), click Shop Order. Verify that the other field values in
the Received Part area change to the information for the 21-313 (Oil
Pan) part.
- Select both the Receive
With Backflush check box and the Auto Report Of Operations check box.
- In the Quantity Received field in the table, enter 2 to receive
the last of the 11 oil pans.
- Save the information.
- Click Yes to indicate that you want to continue after receiving the
system warning that you are receiving more material than was originally ordered and that you would need to manually issue
any additional component
material needed in excess of the quantities allocated for the shop order lot
size. You will not need to manually issue additional material.
- Close the
Receive Shop Order window.
- On the
Detail tab, verify that the Qty Complete
field now displays 11 and that the value in the Products
field has changed to Completely Received.
- Right-click anywhere in the header, and click Close. Verify that
the state of the shop order has changed to Closed. The shop order was able
to close because both the material and the by-product quantities that were reported complete
are within the close tolerance.
- Close the
Shop Order window.
Manually/Automatically Receiving More Than The Shop
Order Lot Size.
Windows:
Receive Shop Orders
If you want to receive more than the planned lot size.
- Open the
Shop Order window and query
for the desired shop order number.
- Right-click anywhere in the header, point to Material Actions, and
then click
Manual Receive.
- When the
Receive Shop Order window displays, select the Backflush check box and the Auto Report Of Operations check box,
in the Material and Operations area.
- On the
Inventory Receipt tab (in the
Receive Shop
Order window), in the Quantity Received field enter a
quantity bigger than the planned lot size.
- When you try to save it, a warning message will be
displayed informing you about the excess quantity. If you wish to continue
click Yes, else click No.
- The received total quantity will now be in the