Reporting Operations on Shop Orders Using Dispatch List—Exercises
Basic Data Setup
Enter Person
Purpose: The purpose of this exercise is to create a new
person record to be used in the main exercise.
Windows:
Person
- Open the
Person window and create a new record.
-
Enter an appropriate name.
- Save the information.
Enter Inventory Parts, Product Structures, Work Centers, Labor Classes and
Routings
Purpose: The purpose of this exercise is to create the
required data that is used in the main exercises. This sets up
data for your site that only needs to be done once for Discrete Manufacturing
exercises.
- Set up your site so that it includes all
the discrete manufacturing data for racing engines.
General
exercise for Overview of Discrete Manufacturing Data
Enter an Inventory Location
Purpose: The purpose of this exercise is to set up
inventory picking locations for running functionality isolated by site.
Windows:
Inventory Locations
- Create the inventory picking locations
shown in the table below.
Site |
Location No |
Warehouse |
Location Description |
Location Group |
Your Site |
1 |
Main |
Main Warehouse |
30 |
General exercise for
Entering Inventory Locations
Required Data
Create an Inventory Part Balance
Purpose: The purpose of this exercise is to
ensure that
you have enough parts to complete the main exercises.
Windows:
Inventory Part Currently On Hand
Receive Inventory Part
- Verify that you have at least the quantity of parts shown on the table
below available for manufacturing. If you do not, receive the indicated
quantity of the parts into inventory location number 1.
Site |
Part Number |
Part Description |
Quantity Available for Manufacturing |
Location No |
Your Site |
21-330 |
Ignition System |
30 |
1 |
Your Site |
21-331 |
Starting System |
30 |
1 |
Your Site |
21-332 |
Battery System |
30 |
1 |
General
Exercise for
Receiving
Inventory Part
Enter Shop Orders
Purpose: The purpose of this exercise is to create the
shop orders that will be used in the main exercises.
Windows:
Shop Order
- Create shop orders for the parts and quantities below. Release each shop
order. Enter the date the order is required on, approximately a week ahead. Write down your shop order numbers so you can easily find the appropriate
shop order for each main exercise.
Site |
Part Number |
Part Description |
Lot Size |
Shop Order Number |
Relevant Exercise |
Your Site |
21-230 |
Electrical System |
10 |
|
Scenario 1, Reporting on Each Operation Using Start / Stop
Functionality |
Your Site |
21-230 |
Electrical System |
10 |
|
Scenario 2, Reporting on Several Operations Simultaneously Using
Start / Stop Functionality |
Your Site |
21-230 |
Electrical System |
10 |
|
Scenario 3, Reporting on Each Operation Using Only Approve
Functionality |
Your Site |
21-230 |
Electrical System |
10 |
|
Scenario 4, Reporting only on Last
Operation Using Approve Functionality |
Your Site |
21-230 |
Electrical System |
10 |
|
Cancel Clockings and Operation Reports Using Dispatch List |
General exercise
for Creating Shop Orders Manually
Labor setup time on operation 10 should be added to all
shop order:
- Click the
Operation tab, make sure
labor class 1 is entered.
- Enter 0,1 in the Labor Setup Time field.
- Save the record.
Main Exercise
Purpose: The purpose of this exercise is to learn how to
enter basic data for dispatch list and use the dispatch list for reporting operations.
Windows:
Shop Order Basic Data
Dispatch List
Create a new filter, connect the filter to a person and view accurate
operations in dispatch list.
- Open the Shop Order
Basic Data window and click the
Dispatch List Filters tab.
- Create a new row in the
Filtersub tab.
-
Enter a filter
name and its description.
- Clear the Selection Executable
check box and select the Selection Released check box. This option shows
all operations on the shop order that are in a state higher than Planned, and
lower than Closed.
- Select the Auto Start Populate check box. When the
Dispatch List
window is opened, data will be populated automatically.
- Select the Auto Start Change Person check box, when the
Dispatch
List window is opened, the
Change Person dialog box will automatically open
up if the person is connected to the logged on user.
- Enter your site and work centre 300. Only operations that belong to work centre 300 will be
shown.
- Save the information.
- Click the
Default Filter per Person tab and create a new row.
- Enter a person, or select one from the List of
Values.
- In the Dispatch List Filter field, enter the filter you have
created to connect as the default filter or select one from the List of Values.
- Save the information.
- Open the
Dispatch List window.
- Enter your person in the
Change Person dialog
box, or select
from list of values. Make sure the filter connected to your person is
defaulted in the Filter field.
- Click OK.
Note: If the dialog box did not
open up automatically click Change Person on the upper right
corner, to open it.
- Make sure the shop order operations created for this exercise
are displayed in the list.
- If preferred, change the filter criteria in the header, e.g.
change the
selection operation to Executable and note that only the first
operation in each shop order will be shown.
Note: In this exercise, reporting should be done on the first shop order created for this exercise.
- Open the
Dispatch List window, make sure the shop
order operations created for this exercise are shown in the list.
If not change the filtering criteria in the header such that they
appear.
- Select operation 10 and then click Start Setup.
The
Start Setup dialog box will appear. On this operation, only labor setup time should be reported. Make
sure only the Labor Time check box is selected. If preferred, change
the crew size and/or add person records that should be connected to the operation
in the table. It is also possible to enter a clocking note text that will be
visible while the setup is running.
- Click OK and the clock for setup labor
time will start.
- Wait a few minutes to simulate setup is
being finished, then click Stop Setup.
The
Stop Setup dialog box will appear.
- In the dialog box, click OK and the clock for
labor setup time will stop counting.
- Verify that a clocking has been created in the
Clockings
tab, and a transaction has been created in the
Operation Report tab.
- On the same operation, click Start Production.
The
Start Production dialog box will appear.
- Both labor and machine time should be reported,
therefore make
sure that the Machine Time and Labor Time check boxes in the
dialog box are selected.
- Click OK
to start the clock for machine run time.
- Wait a few minutes to simulate some production
has been performed, then click Stop Production. The
Stop
Production dialog box will appear.
- To simulate that production had to be stopped due
to some kind of interruption, select Interrupted in the Stop Reason
list and if preferred, enter an appropriate note in the Interruption Note field.
- Click OK and the clock for machine
production time will stop counting.
- Verify that another clocking has been created in the
Clockings
tab and that two more transactions have been created in the
Operation Report tab.
- Resume production again for the operation by
clicking Start Production and then click OK in the dialog box
that appears.
- Wait a few minutes to simulate production is being
finished and then click Approve Operation.
- In the
Approve Operation dialog box, make sure that the entire quantity is being reported
in the Qty to Report field. Also make sure that the Close Operation
and Stop Time check boxes are selected.
- Click OK. This will stop and report the production
time, report quantity as finished, and close operation. The operation will
disappear from the dispatch list.
- Select operation 20. On this operation only production
time for
machine and labor should be reported.
- Repeat appropriate steps above (7, 8, 9, 15, 16
and 17).
- Select operation 30. On this operation production time for
both
machine and labor time should be reported.
- Repeat appropriate steps above (7, 8, 9 and 15),
- Because operation 30 is the last operation on the shop order, the
Receive area in the
Approve Operationdialog box will be enabled. Make
sure the check boxes Close Operation, Stop Time, and
Receive Into Inventory are selected. Also make sure the full
quantity is entered in the Qty to Report field and in Qty to
Receive field.
- Enter 1 in the Receive Into Location field, or
select one from the List
of Values.
- Click OK. This will stop and report the production
time, report quantity as finished, and close the operation. It will also receive
the parts into inventory and set the status of the shop order to Closed.
Note: The start/stop feature only
counts time within the calendar, i.e., if the calendar has work time defined
between 8 A.M.-12 noon and 1 P.M.-5 P.M. and time is started at 11:45 A.M. and stopped
at 1:00 P.M., only 15 minutes
time will be reported.
Note: In this exercise, reporting should be done on the second shop order created for this exercise.
- Select operation 10 and report some labor
setup time by clicking Start/Stop Setup as in the previous scenario.
- On operation 10 and 20, production machine and
labor time should be reported
simultaneously, therefore select both operations 10 and 20 and click
Start Production.
- Start the clock for production machine and labor
time by clicking OK.
- Wait a few minutes to simulate the production
which is being performed
for both operations 10 and 20.
- Select one of the operations and click Stop Production.
- Stop the clock for production machine and labor
time by clicking OK.
This will stop the clock for both operations, and the production time will be divided between the two operations
proportionately according to the Machine Run Factor on the shop order.
- Click the
Operation Reportstab to view the time reported.
Verify that operation 20 has received twice as much manufacturing time
as operation 10. (Because operation 20 has 1 hour planned manufacturing
time and operation 10 has 0.5 hours).
- Close operation 10 and then operation 20 by
clicking Approve Operation.
- Select operation 30 and report machine and labor production time by
using the
Start Production dialog box.
- Stop the production time, close operation 30, close the shop order
and receive parts into inventory location 1 using the
Approve
Operation dialog box.
Note: To report operations simultaneously they
should belong to the
same work center.
Note: In this exercise reporting should be done on the third
shop order created for this exercise.
- Select operation 10 and click Approve Operation.
The Approve Operation dialog box will open.
- In the dialog box, make sure the entire quantity is entered in the Qty to
Report field.
Note: It is only possible to use the
Approve
Operation dialog box when you have a quantity to report; i.e., it is not
possible to use the dialog box if you have no (zero) quantity to report.
- Make sure the check boxes Close Operation and Report Time are selected.
- If preferred, change the time to report in the Operation Time
area. The default value is the time from the shop order.
- Click OK to report time, issue connected components
and close operation.
- Repeat step 1 to 5 for operation 20.
- Select operation 30 and click Approve Operation.
- Since this is the last operation on the shop order the
Receive area will be enabled.
- Make sure the entire quantity is entered in the Qty to Report and
Qty to Receive fields.
- Make sure the Close Operation, Report Time and
Receive into
Inventory check boxes are selected.
- If preferred, change the time to report in the Operation Time
area.
- Enter 1 in Receive Into Location field or
select a value from the List of Values.
- Click OK in order to report and close operation 30, close the
shop order and receive parts into inventory location 1.
Note: In this exercise reporting should be done on the fourth shop order created for this exercise.
- Select operation 30 on the shop order and
click Approve Operation. The
Approve Operation dialog
box will open.
- In the dialog box, make sure the entire quantity
is entered (if not a partial receipt) in the Qty to
Report and Qty to Receive fields.
- Make sure the Close Operation, Report Previous Operation,
Report Time
and Receive into Inventory check boxes are selected.
- Select the Receive with Backflush check box.
Note: If you select the
Simplified Material Check check box, you do not need to issue planned quantity of
materials but all materials need to be in the Issued status. That is, at least some
quantity needs to be issued before using the Simplified Material Check
check box to
skip the issue of materials.
- If preferred, change the time to report on operation 30 in the
Operation Time area.
- Enter 1 in Receive Into Location field or
select a value from the List of Values.
- Click OK in order to report and close operation 10, 20 and 30,
issue material/skip issue material, close the shop order and receive parts into inventory
location 1.
Note: When performing
a partial receipt and you wish to close the shop order at the same time you have to
select the
Close Shop Order check box.
Note: In this exercise reporting should be done on the fifth shop order created for this exercise.
- Select operation 10 and register some labor
setup time by clicking
Start/Stop Setup as you have done previously.
- On the same operation, register some machine and
labor production time by clicking Start/Stop Production.
- Click the
Operation Reports tab and verify that you have
received three transactions, one for labor setup time, one for machine
production time, and one for labor production time.
- Click the
Clockings tab and verify that you have received two
records, one for setup time, and one for run time.
- Select the record for run time, right-click and then
click Cancel Stop to cancel
the stopping of production. The clock for machine production time will be
running again.
-
Refresh the operation list by clicking Refresh.
Verify that the operation now has a green symbol to the left indicating
production time is running.
-
Stop the time again by clicking Stop Production.
-
Now cancel the start of the setup time on the operation
by selecting it in the
Clocking tab, right-clicking and then
clicking Cancel Start. Verify that the
entire record is removed from the table.
-
Also verify that the transaction for
labor setup time has been removed
from the
Operation Reports tab.
-
Report quantity and close operation 10 by
clicking Approve.
-
Select operation 20 and click Approve.
-
Report only half quantity so that the operation not will be
closed. Make sure the Report Time check box is selected and values
are entered in Machine Time and Labor Time fields.
-
Click OK.
-
Click the
Operation Reports
tab and verify
three
transactions are created, one for machine production time, one for labor
machine time and one for quantity.
-
Cancel the transactions by right-clicking
and then clicking the appropriate option.
-
If preferred, finish the reporting on the operation. Also
try to cancel from Operation Reports when the transactions have been
created from clockings (start/stop functionality has been used. Then an
error message will appear because these transactions must be canceled from
the
Clockings tab.