Setting Project Baselines—Exercises
Required Data
Approving and Starting Projects
Purpose: The purpose of this exercise is to show you the
required data that is used in the exercises below.
- Approve and start your project.
General exercise for
Approving and Starting Projects
Executing Activities
Purpose: The purpose of this exercise is to familiarize
you with the data that must be in place before you can perform the exercises below.
In order to understand baseline functionality, project activities need to both
have planned values and get calculated progress. The exercise below will use
tasks in order to plan and execute activities.
- Following the main exercise below, connect some tasks to some activities. Enter planned values.
- Following the main exercise below, execute your activities by
reporting progress on the tasks.
General exercise for Creating and Connecting Tasks
and Using Tasks to
Report Progress
Main Exercise
Purpose: The purpose of these
exercises is to show you how to
set project baselines. You will learn how project indicators such as Earned
Value and Scheduled Work are calculated depending on the value of the Earned
Value Method. This lesson will help you understand how changes to the project plan
can be handled with the help of
baseline functionality.
Windows:
Project Navigator/Activity
Projects
Project
- Open the
Project
Navigator window and query for your project.
- Enter a task on an activity and enter values
for that task in the Planned Hours field and the Planned Cost field
for a cost element. (See the
Required Data section of this exercise.)
- Click the
Activity tab and then the
Cost
tab and the Hours
tab, note that the values in the Planned column are updated from the
task. (The value in the Planned Cost Driver field must be
Connected Objects.)
- Select the highest level in the project navigator of the
Project
Navigator window, right-click and then click Set Baseline to open
Set Baseline dialog box. This action can also be done in the
Projects or
Project window.
- Note that the project ID and baseline revision number
are shown as information.
- Select the value Baseline from the Earned
Value Method list.
- Optionally you can add a comment in the Comment field.
- Click OK. The baseline revision is created for
your project.
- Note that the baseline revision number and chosen
Earned Value Method are shown in the header of the
Project
Navigator
window.
- In the project navigator, select your activity from
step 2 and click the
Activity tab.
- On the
Cost
tab, note that the
values in the Baseline Cost column are equal to the values in the Planned
Cost
column. On the Hours tab the values in the Baseline Hours
column will be equal to the Planned Hours column.
- Click the
Details tab. Note that the
dates in the Baseline Start and Baseline Finish fields are
equal are equal to the values in the Early Start and Early Finish
fields.
- Execute your activity by reporting progress on the
task created in step 2. (See the Required Data section of this exercise.)
Make sure that the value in the Early Start field is earlier than
today's date.
- Click the
Cost and
Hours tabs. Note the
values in the Scheduled Work and Earned Value columns.
Note: Scheduled work
values shows the budgeted cost or hours scheduled
to be completed at the current date if the budgeted values had been evenly
distributed over the activity's work days. As the Earned Value Method is
Baseline, the budgeted values are equal to the baseline values.
Note: The earned value is the budget cost
or hours for the
work actually performed, based on the progress. Since the Earned Value Method is
Baseline, Earned Value Cost = Progress on the Task line * Baseline Cost
and Earned Value Hours = Progress on the Task line * Baseline Hours.
- Change
the planned cost value for the task
created in step 2.
- Click the
Cost tab and
observe that
the values in the Planned column are updated according to your
changes. Note that the values in the Baseline, Earned Value and Scheduled Work
columns are unchanged.
- Repeat steps 4-8 to create a second baseline for your
project, with the difference that you should select the value Planned
from the Earned Value Method list.
- In the project navigator, select your activity from
step 2 and click the
Activity tab. On the
Cost
and Hours
tabs, note the values in the Planned, Baseline, Scheduled
Work and Earned Value columns.
- Change either the planned
cost or the planned hours for the task created in
step 2.
- Click the
Cost
and Hours tabs and observe that
the value in the Planned column are updated according to your
changes. Note that the values in the Baseline column will remain unchanged.
The values in the Earned Value and Scheduled Work
columns will also be updated and are now calculated based on the values in the
Planned column, instead of the baseline values.
- Open the
Project
Navigator window and query
for your project.
- Perform steps 4-8 described above in the Setting
Project Baselines exercise, to create a new baseline revision.
- Change a planned value for an activity. For example,
you can change some planned values for the task created in step 2 of the
above exercise.
- In the project navigator, select this activity and
click the
Activity tab. Note that the Activity Changed check box has been selected
because a value in the Planned column differs from the value in the
Baseline column.
- Select another activity in the project navigator and
on the
Activity tab, change the value of the Early Start
or Early Finish field.
- Note that the Activity Changed check box has been selected
because a value in the Early Start or Early Finish field
differs from the value in the Baseline Start or respectively the
Baseline Finish field.
- Create a new activity in your project structure. Note that the Activity Changed check box has been selected.
- Perform steps 4-8 described above in the Setting
Project Baselines exercise, to create a new baseline revision. Note the
value of the baseline revision which you are creating.
- For each of the activities you changed, note in the
Activity tab that the new baseline revision is the value shown
in the Set in Baseline and Baseline Revision Comment
fields.
- Note also that the Activity Changed check box
has been cleared.