Creating Project Budget/Forecast—Exercises
Basic Data Setup
Budget/Forecast Type
Purpose: The purpose of this exercise is to set up the basic
data required for running this particular functionality.
Windows:
Project Basic
- Create a forecast with the forecast type GEN (with the Set as Budget
check box unselected) and a budget with the budget type BGT (with
the Set as Budget check box unselected) .
General exercise for
Enter Budget/Forecast Type.
Required Data
Create Activities
Purpose: The purpose of this exercise is to familiarize you with the data
that must be in place before you can perform the exercises below.
- Create a project in company 10 and create activities in your subproject
structure.
General exercise for Building
Project Plan.
Create an Approval Template
Purpose: The purpose of this exercise is to show you the
required data that is used in the exercises below.
- Open the Document
Basic window and click on the
Approval Template tab.
- Create an approval template in which you are the member who approves the
first step.
General exercise for
Create an Approval
Template .
Define Cost Element Code Part Demands
Purpose: The purpose of this exercise is to show you the
required data that is used in the exercises below.
- For your company, select the Account check box for the MAT
and LABOR cost elements.
General exercise for
Define Cost Element Code
Part Demands.
Connect Project Cost Elements to Account
Purpose: The purpose of this exercise is to show you the
required data that is used in the exercises below.
- Open the Project
Cost/Revenue Element per Code Part Value window and enter the following
values.
Account |
Project Cost Element |
1400 |
LABOR |
1151 |
MAT |
General exercise for
Connecting Project Cost Element to Account.
Main Exercise
Purpose: The purpose of these exercises is to create a project
forecast as a forecast and as a budget, to enter version lines on the budget and
to enter an approval routing on it.
Windows:
Project
Project Forecasts Info
Project Forecasts
Defining Cost Element
Code Part Demands on Project
Purpose: The purpose of this exercise is to show you how
to define cost element code part demands on a particular project.
- Open the Project
window and query for your project.
- Click on the PCE Code Part Info
tab.
- Select the check boxes in the Account field for the LABOR
and MAT cost elements.
- Click Save.
Creating Project Forecast
- Open the Project
window and query for the project.
- Right-click and click Create Forecast.
- Select the value GEN from the List for the Forecast Type
field.
- Enter Version 1, in the Version Description field.
- Click OK. A message box opens, inquiring whether you wish to view
the project forecast, click Yes.
- Review the information in the
Project Forecast Info window.
Creating Project Budget
- Open the Project
window and query for the project.
- Right-click and click Create Forecast.
- Select the value BGT from the List for the Forecast Type
field.
- Enter Version 1, in the Version Description field.
- Click OK. A message box opens, inquiring whether you wish to view
the project forecast, click Yes.
Entering Budget/Forecast Lines
- Open the Project Forecast Info window
and query for the project budget.
- Select the activity node in the project (left hand side of the window).
- Select LABOR in the Cost Element field of the
Cost tab.
- Enter 10000 in the ETC field.
- Select 1440-LAB in the Account field.
- Select MAT in the Cost Element field of the
Cost tab.
- Enter 10000 in the ETC field.
- Select 1440-MAT in the Account field.
- Save the record (F12).
Entering Approval
Routing on Project Budget/Forecast
- Open the Project
Forecasts window and query for the project budget that you created.
- Select the row, right-click and click Project Forecast Info.
- Click the Approval Routing tab.
- Select a row, right-click and click Copy Approval Template.
- Use the List to select the approval template that you created, and
click OK.