Retrieving Used and Actual Costs to Project—Exercises
Required Data
Creating Inventory Transactions
Purpose: The purpose of this exercise is to familiarize
you with the data that must be in place before you can perform the exercises
below.
- Case 1: Create inventory transactions by purchasing inventory parts to an
activity in your project. Complete the purchasing process until the
purchased parts have been received into project inventory. (For example,
purchase part number 96-2000 to activity 20020 and receive into project inventory.)
- Case 2: Create further inventory transactions by issuing some of these
purchased inventory parts from the project inventory. (Issue the received part 96-2000 to activity
20020.)
- Case 3: Create inventory transactions also by issuing standard material
directly to an activity, without going through the purchasing process.
(Issue part 96-1000 directly from standard inventory to activity 20010.)
Note: This exercise refers to the following examples:
Case |
Activity ID |
Purchase Part No. |
Case 1: Receive inventory parts procured through project PO |
20020 |
96–2000 |
Case 2: Issue of inventory parts procured through project PO |
Case 3: Direct issue of standard inventory parts |
20010 |
96–1000 |
General exercise for
Purchasing Project
Miscellaneous Demand and
Issuing
Material From Inventory
Main Exercise
Purpose: The purpose of this exercise is to show you how
to retrieve used and actual costs to your project.
Windows:
Inventory Transactions History
Transfer Inventory Transactions
Project Navigator/Activity
Project Navigator/Connections
Update GL Vouchers
- Open the
Inventory Transactions History
window.
- Query for your site and for your part numbers, both the part procured
through purchasing (96-2000) and the part directly issued to your project
activity from standard inventory (96-1000).
- Select the rows, right-click and then click
Inventory Transaction
History.
- Click the
General tab and view each transaction.
- Note which transaction codes are associated with each case, as performed
in the required data section of this exercise. (See the table below for the
data you should expect to see.)
- Click the
Accounting tab.
- Note the inventory transaction values for each
transaction. Verify which posting types are posted with the project ID and
activity sequence number. (See the table below for the data you should
expect to see.)
Note: The postings should have the status code 2 (Completed).
If a posting has received the status 99 (Incorrect accountings), some Posting
Control basic data has been incorrectly set up in IFS Accounting Rules.
- Open the
Project Navigator window and query for your project.
- In the Navigator, select the activity on which you
procured the part through purchasing and then issued some from the project
inventory.
- Click the
Activity
tab. On the
Cost tab, note that the values in the
Used column are updated, based on the inventory transaction value
from the ARRIVAL transaction. Note that issuing from project inventory does
not result in further used costs. Verify that the values update the correct
cost elements, based on how you set up the relevant posting control rule and
cost element mappings.
- In the Navigator, select the activity on which you
issued directly from standard inventory.
- On the
Cost tab, note that the values in the
Used column are updated, based on the inventory transaction value
from its PROJISS transaction. Verify that the values update the correct cost
elements, based on how you set up the relevant posting control rule and cost
element mappings.
- Open the
Transfer
Inventory Transactions window.
- If your project site is not shown by default, select it from the List of
Values.
- Click OK to transfer the inventory transactions to the financial
system.
Note: This is a background job that must be completed before you can
continue.
- Return to the
Inventory Transactions History
window. Query for your site and part numbers once again.
- Select the rows, right-click and then click
Inventory Transaction
History.
- View each transaction. Click the
Accounting
tab and note that a voucher number has been connected to the transactions.
- In the
Project
Navigator window, click the
Activity
tab. View each activity and note that values in the Used column
have not changed.
- Click the Connections tab. Observe that
the associated hold table voucher rows are listed, and that they are
updating the values for Used Cost.
- Open the
Update GL Vouchers window.
- Verify that the window specifies the company with which you are working,
i.e., Company 10.
- On the
Selection tab, click Select Vouchers.
- Select the relevant vouchers, i.e., the MPL
vouchers as shown on the inventory transactions in step 18. Click OK.
- A message appears informing you which journal number has been created.
Click OK.
- Return to the
Project
Navigator window.
- In the Navigator, select each activity to view the
values in the Actual
column. On the
Cost and
Hours tabs, note that the values in the Actual
column are updated. Verify that the values update the correct cost elements,
based on how you set up the relevant posting control rule and cost element
mappings.
- Click the Connections tab. Observe that
the hold table voucher rows have been replaced by General Ledger voucher
rows, and that they are updating the values for both Used Cost and
Actual Cost.
Note: The following is a summary of what you should see for each case:
Case |
Transaction Code |
Posting Type |
Posted with Project ID and Activity Seq. No. |
Activity |
Used and Actual Cost Updated |
Case 1: Receive inventory parts into
project inventory, procured through project PO |
ARRIVAL |
M1 |
yes |
20020 |
Material: equal to inventory transaction value |
M10 |
no |
Case 2: Issue of inventory parts from
project inventory, procured through project PO |
PROJISS |
M1 |
yes |
20020 |
Material - both debit and credit, no additional costs are retrieved to the
activity |
M62 |
yes |
Case 3: Direct issue of inventory parts
from standard inventory |
PROJISS |
M1 |
no |
20010 |
Material: equal to inventory transaction value |
M62 |
yes |
Copying forbidden: The material in this manual is protected by copyright law, and may not be copied entirely or in part, without the prior permission of Industrial & Financial Systems AB. © 2012 Industrial & Financial Systems AB